๐Ÿ“Review Complete๐Ÿ”ง Renovation/Alteration๐Ÿ’ต This project involves public funds, public land, or is a Federally funded roadway project.

CBP Security at Global Entry Office in Terminal D at DFW Intl. Airport

2333 S International Pkwy, Dfw Airport, TX 75261, Dfw Airport, TX, 75261
Construction50%

๐Ÿ“ŠProject Metrics

TDLR #TABS2020022173
$78K
Project Value
250
Square Feet
$311/sqft
Cost/SqFt
4 months
Duration
Registered:Aug 13, 2020
Start:Oct 1, 2020
Target:Jan 27, 2021
๐Ÿ“

Review Complete

Design review complete, construction may proceed

๐Ÿ“‹Scope of Work

The existing public entrance doorway to the CBP Global Entry Office will be upgraded for higher security and a pass-through window will be added.

Note: This project is registered under the Texas Accessibility Standards (TAS) program. TDLR registration is required for commercial and public facility construction to ensure compliance with accessibility requirements under Texas Government Code Chapter 469.

๐Ÿ“…Compliance Timeline

Project Registered
August 13, 2020
Construction Start
October 1, 2020
Expected Completion
January 27, 2021