๐ŸProject Closed๐Ÿ—๏ธ New Construction๐Ÿ’ต This project is privately funded, on private land for private use.

Starbucks - Jarrell

C. Bud Stockton Loop, Jarrell, TX 76537, Jarrell, TX, 76537
Completed100%

๐Ÿ“ŠProject Metrics

TDLR #TABS2022016323
$850K
Project Value
2,390
Square Feet
$356/sqft
Cost/SqFt
4 months
Duration
Registered:Apr 11, 2022
Start:Jun 1, 2022
Target:Oct 1, 2022
๐Ÿ

Project Closed

Project has been completed and closed

๐Ÿ“‹Scope of Work

1 Exterior building shell with slab on grade foundation, wood stud construction, fiber cement siding, vertical tile, mechanical, electrical, and plumbing work. Project will include utilities work, concrete paving & landscaping

Note: This project is registered under the Texas Accessibility Standards (TAS) program. TDLR registration is required for commercial and public facility construction to ensure compliance with accessibility requirements under Texas Government Code Chapter 469.

๐Ÿ“…Compliance Timeline

Project Registered
April 11, 2022
Construction Start
June 1, 2022
Expected Completion
October 1, 2022

Quick Actions

TDLR ID: TABS2022016323

Registered Accessibility Specialist

๐Ÿ“‹
JESSICA TREVINO,HAMM
RAS #1429
1218 E EUCLID AVE, SAN ANTONIO, TX 78212