โœ…Inspection Complete๐Ÿ—๏ธ New Construction๐Ÿ’ต This project involves public funds, public land, or is a Federally funded roadway project.

Water Utilities Building-City of Garland

2343 Forest Lane, Garland, TX 75042, Garland, TX, 75042
Final Inspection85%

๐Ÿ“ŠProject Metrics

TDLR #TABS2022022801
$13.5M
Project Value
27,229
Square Feet
$497/sqft
Cost/SqFt
1y 1mo
Duration
Registered:Jun 30, 2022
Start:Aug 29, 2022
Target:Sep 11, 2023
โœ…

Inspection Complete

Final inspection completed, awaiting project closure

๐Ÿ“‹Scope of Work

Ground up facility for the Water Department for Garland. Includes new site utilities, paving, landscape and irrigation. Demo of existing bldgs on site to allow for the expansion of existing parking lot.

Note: This project is registered under the Texas Accessibility Standards (TAS) program. TDLR registration is required for commercial and public facility construction to ensure compliance with accessibility requirements under Texas Government Code Chapter 469.

๐Ÿ“…Compliance Timeline

Project Registered
June 30, 2022
Construction Start
August 29, 2022
Expected Completion
September 11, 2023