๐ŸProject Closed๐Ÿ”ง Renovation/Alteration๐Ÿ’ต This project involves public funds, public land, or is a Federally funded roadway project.

Alicia R. Chacon International School-HVAC Upgrades and other Improvements

920 Burgundy Drive, El Paso, TX 79907, El Paso, TX, 79907
Completed100%

๐Ÿ“ŠProject Metrics

TDLR #TABS2022022855
$5.0M
Project Value
94,815
Square Feet
$53/sqft
Cost/SqFt
1 year
Duration
Registered:Jul 1, 2022
Start:Aug 1, 2022
Target:Aug 1, 2023
๐Ÿ

Project Closed

Project has been completed and closed

๐Ÿ“‹Scope of Work

HVAC upgrades throughout and miscellaneous interior improvements; wall removal/replacement, millwork replacement, door and plumbing fixture replacement, and finishes.

Note: This project is registered under the Texas Accessibility Standards (TAS) program. TDLR registration is required for commercial and public facility construction to ensure compliance with accessibility requirements under Texas Government Code Chapter 469.

๐Ÿ“…Compliance Timeline

Project Registered
July 1, 2022
Construction Start
August 1, 2022
Expected Completion
August 1, 2023