๐ŸProject Closed๐Ÿ”ง Renovation/Alteration๐Ÿ’ต This project is privately funded, on private land for private use.

Emerson Main Entrance

4725 S US Highway 75, Sherman, TX 75090, Sherman, TX, 75090
Completed100%

๐Ÿ“ŠProject Metrics

TDLR #TABS2023005594
$1.0M
Project Value
2,216
Square Feet
$451/sqft
Cost/SqFt
4 months
Duration
Registered:Nov 16, 2022
Start:Nov 21, 2022
Target:Mar 11, 2023
๐Ÿ

Project Closed

Project has been completed and closed

๐Ÿ“‹Scope of Work

Renovation and expansion of facility's existing lobby.

Note: This project is registered under the Texas Accessibility Standards (TAS) program. TDLR registration is required for commercial and public facility construction to ensure compliance with accessibility requirements under Texas Government Code Chapter 469.

๐Ÿ“…Compliance Timeline

Project Registered
November 16, 2022
Project Closed
March 11, 2023
Construction Start
November 21, 2022
Expected Completion
March 11, 2023