๐Ÿ“Review Complete๐Ÿ”ง Renovation/Alteration๐Ÿ’ต This project involves public funds, public land, or is a Federally funded roadway project.

Springbrook Village Offsite Grading, Drainage and Sidewalk

9951 Clay Road, Houston, TX 77080, Houston, TX, 77080
Construction50%

๐Ÿ“ŠProject Metrics

TDLR #TABS2023010522
$80K
Project Value
1,100
Square Feet
$73/sqft
Cost/SqFt
4 months
Duration
Registered:Jan 30, 2023
Start:Feb 13, 2023
Target:Jun 2, 2023
๐Ÿ“

Review Complete

Design review complete, construction may proceed

๐Ÿ“‹Scope of Work

remove and replace existing 4' sidewalk with 6' sidewalk

Note: This project is registered under the Texas Accessibility Standards (TAS) program. TDLR registration is required for commercial and public facility construction to ensure compliance with accessibility requirements under Texas Government Code Chapter 469.

๐Ÿ“…Compliance Timeline

Project Registered
January 30, 2023
Construction Start
February 13, 2023
Expected Completion
June 2, 2023