โœ…Inspection Complete๐Ÿ”ง Additions to Existing Building๐Ÿ’ต This project involves public funds, public land, or is a Federally funded roadway project.

Foster High School

4400 Farm to Market Rd 723, Richmond, TX 77406, Richmond, TX, 77406
Final Inspection85%

๐Ÿ“ŠProject Metrics

TDLR #TABS2023018637
$14.8M
Project Value
42,355
Square Feet
$349/sqft
Cost/SqFt
1y 1mo
Duration
Registered:May 9, 2023
Start:Jun 21, 2023
Target:Jul 12, 2024
โœ…

Inspection Complete

Final inspection completed, awaiting project closure

๐Ÿ“‹Scope of Work

Cafeteria, classroom and gymnasium additions to existing Foster High School.

Note: This project is registered under the Texas Accessibility Standards (TAS) program. TDLR registration is required for commercial and public facility construction to ensure compliance with accessibility requirements under Texas Government Code Chapter 469.

๐Ÿ“…Compliance Timeline

Project Registered
May 9, 2023
Construction Start
June 21, 2023
Expected Completion
July 12, 2024