๐Ÿ“Review Complete๐Ÿ—๏ธ New Construction๐Ÿ’ต This project involves public funds, public land, or is a Federally funded roadway project.

New Fire Station Jamestown

24971 CR 453, Mineola, TX 75773, Mineola, TX, 75773
Construction50%

๐Ÿ“ŠProject Metrics

TDLR #TABS2023022843
$3.4M
Project Value
8,468
Square Feet
$402/sqft
Cost/SqFt
9 months
Duration
Registered:Jul 5, 2023
Start:Jul 28, 2023
Target:Apr 30, 2024
๐Ÿ“

Review Complete

Design review complete, construction may proceed

๐Ÿ“‹Scope of Work

Project consists of the construction of a new, approximate 8,468 SF fire station which includes 2,750 SF of R3 occupancy and approximately 5,898 SF of truck bays and accessory spaces(S2 Occupancy).

Note: This project is registered under the Texas Accessibility Standards (TAS) program. TDLR registration is required for commercial and public facility construction to ensure compliance with accessibility requirements under Texas Government Code Chapter 469.

๐Ÿ“…Compliance Timeline

Project Registered
July 5, 2023
Construction Start
July 28, 2023
Expected Completion
April 30, 2024