📝Review Complete🏗️ New Construction💵 This project is privately funded, on private land for private use.
Shell Building Handley Ederville
1929 handley ederville, Fort Worth, TX 76168, Fort Worth, TX, 76168
Construction50%
📊Project Metrics
TDLR #TABS2024007610$1.3M
Project Value
26,250
Square Feet
$50/sqft
Cost/SqFt
2y 1mo
Duration
Registered:Dec 18, 2023
Start:Jun 1, 2024
Target:Jun 30, 2026
Remaining:185 days
📝
Review Complete
Design review complete, construction may proceed
📋Scope of Work
Develop site and build new shell building for later occupancy and finish-out by a tenant
Note: This project is registered under the Texas Accessibility Standards (TAS) program. TDLR registration is required for commercial and public facility construction to ensure compliance with accessibility requirements under Texas Government Code Chapter 469.
📅Compliance Timeline
Project Registered
December 18, 2023
Construction Start
June 1, 2024
Expected Completion
June 30, 2026