๐ŸProject Closed๐Ÿ—๏ธ New Construction๐Ÿ’ต This project is privately funded, on private land for private use.

Brakes Plus

114 Beach Street, Fort Worth, TX 76111, Fort Worth, TX, 76111
Completed100%

๐Ÿ“ŠProject Metrics

TDLR #TABS2024009814
$1.7M
Project Value
4,800
Square Feet
$354/sqft
Cost/SqFt
3 months
Duration
Registered:Jan 22, 2024
Start:Mar 1, 2024
Target:Jun 1, 2024
๐Ÿ

Project Closed

Project has been completed and closed

๐Ÿ“‹Scope of Work

Ground up construction of an automobile repair facility with associated site work

Note: This project is registered under the Texas Accessibility Standards (TAS) program. TDLR registration is required for commercial and public facility construction to ensure compliance with accessibility requirements under Texas Government Code Chapter 469.

๐Ÿ“…Compliance Timeline

Project Registered
January 22, 2024
Construction Start
March 1, 2024
Expected Completion
June 1, 2024