๐Project Closed๐ง Renovation/Alteration๐ต This project is privately funded, on private land for private use.
HPD Terminal A Temporary Relocation
2800 N. Terminal Rd. 2800 N. Terminal Rd., Houston, TX 77032, Houston, TX, 77032
Completed100%
๐Project Metrics
TDLR #TABS2024012298$212K
Project Value
2,118
Square Feet
$100/sqft
Cost/SqFt
5 months
Duration
Registered:Feb 23, 2024
Start:Mar 29, 2024
Target:Aug 30, 2024
๐
Project Closed
Project has been completed and closed
๐Scope of Work
INTERIOR RENOVATION OF TERMINAL A. RENOVATION TO INCLUDE MODIFICATION OF WALLS, NEW FINISHES & ELECTRICAL
Note: This project is registered under the Texas Accessibility Standards (TAS) program. TDLR registration is required for commercial and public facility construction to ensure compliance with accessibility requirements under Texas Government Code Chapter 469.
๐ Compliance Timeline
Project Registered
February 23, 2024
Construction Start
March 29, 2024
Expected Completion
August 30, 2024
๐Related Projects
๐คSame Owner
$786K totalProperty Owner
๐ค
Houston Airport System
Contact: Anthony W. Brown Esq.
4 projects ยท $786K
View all projects
16930 John F. Kennedy Blvd., Houston, Texas 77032
Design Firm
๐๏ธ
ENGLISH + ASSOCIATES ARCHITECTS, INC
4 projects ยท $7.3M
View company profile
1919 Decatur St., Houston, Texas 77007