๐Review Complete๐๏ธ New Construction๐ต This project involves public funds, public land, or is a Federally funded roadway project.
Pleasanton/Moursund HSIP Improvements (0915-12-695)
Moursund Blvd & Loop 410 to Pleasanton Rd & Fitch, San Antonio, TX 78221, San Antonio, TX, 78221
Construction50%
๐Project Metrics
TDLR #TABS2024019390$122K
Project Value
1,000
Square Feet
$122/sqft
Cost/SqFt
1y 2mo
Duration
Registered:May 27, 2024
Start:Jun 30, 2024
Target:Aug 30, 2025
๐
Review Complete
Design review complete, construction may proceed
๐Scope of Work
Construction of Pedestrian Mid-Block Crossings at various locations
Note: This project is registered under the Texas Accessibility Standards (TAS) program. TDLR registration is required for commercial and public facility construction to ensure compliance with accessibility requirements under Texas Government Code Chapter 469.
๐ Compliance Timeline
Project Registered
May 27, 2024
Construction Start
June 30, 2024
Expected Completion
August 30, 2025
๐Related Projects
๐คSame Owner
$242K totalProperty Owner
๐ค
City of san Antonio
Contact: Daniel Hinojosa
2 projects ยท $242K
View all projects
100 W. Houston St., 16th Floor, San Antonio, Texas 78205
Design Firm
๐๏ธ
Kimley-Horn and Associates, Inc.
4 projects ยท $9.6M
View all projects
10101 Reunion Place, Ste. 400, San Antonio, Texas 78216