CP1029402 UT Restroom Renovations - Parlin Hall (Phase 2) is a renovation/alteration project at 208 West 21st Street, Austin, in Travis County, TX, tracked from its Texas Department of Licensing and Regulation (TDLR) registration. Construction complete (TDLR inspection passed Jun 2026). The project has an estimated value of $969K across about 1,727 sq ft.
Final inspection completed, awaiting project closure
CP1029402 UT Restroom Renovations - Parlin Hall (Phase 2) is a Renovation/Alteration project located at 208 West 21st Street, Austin, TX 78705 in Austin, Texas. The project has an estimated value of $969K covering 1,727 sq ft. University of Texas is the property owner and WestEast Design Group is the design firm of record. The project was registered with TDLR on February 3, 2026.
CP1029402 UT Restroom Renovations - Parlin Hall (Phase 2) is a renovation/alteration project at 208 West 21st Street in Austin, Texas, registered with the Texas Department of Licensing and Regulation (TDLR). Scope of work: ADA remediation for all existing restrooms, approximately 1,727 SF.
Construction on CP1029402 UT Restroom Renovations - Parlin Hall (Phase 2) is complete โ TDLR records show the project passed its required accessibility inspection in Jun 2026. The building is finished and very likely open.
CP1029402 UT Restroom Renovations - Parlin Hall (Phase 2) is located at 208 West 21st Street, Austin, TX, 78705, in Travis County.
University of Texas is the property owner/developer of record for CP1029402 UT Restroom Renovations - Parlin Hall (Phase 2), per its TDLR project registration.
WestEast Design Group is the design firm of record for CP1029402 UT Restroom Renovations - Parlin Hall (Phase 2), according to its TDLR filing.
CP1029402 UT Restroom Renovations - Parlin Hall (Phase 2) has an estimated construction value of $969K and approximately 1,727 square feet (about $561/sqft), based on its TDLR filing.
ADA remediation for all existing restrooms, approximately 1,727 SF.
Note: This project is registered under the Texas Accessibility Standards (TAS) program. TDLR registration is required for commercial and public facility construction to ensure compliance with accessibility requirements under Texas Government Code Chapter 469.
Filed
Feb 3, 2026
Review Complete
Mar 11, 2026
Inspection Complete
Jun 20, 2026
Closed
36d
Review duration
101d
Construction phase
Building permits found at or near this location
Replacement of mini-split system
Repair grease line for grease trap located on Ground floor back of the building near loading dock.
2026/03/12 - 2026/03/18 | (2026/03/11 - 2026/03/19) | Ledger is a sponsor of SXSW and will organize a basketball activation outdoors. This consists of a shootaround structure (metal structure with basketball hoops) basketballs trussing and a net. Participants come to shoot a ball and enter for a chance win a prize (merch). There will be no food or drinks given out during this activation. #SXSWAffiliated
2026/03/12 - 2026/03/18 | (2026/03/06) | Rivian event and activations for SXSW 2026 events
alteration of an existing office space including access control new exterior overhead door site work planters and stairs/landing