✅ Approved and Released
Northtown Municipal Utility District Administrative Office and Park
The applicant proposes to construct an office building, park pavilion and parking with associated improvements.
📍 700 E WELLS BRANCH PKWY, AUSTIN, TX, 78660📄 Site Plan🏛️ AUSTIN 2 MILE ETJ
Entitled100%
Timeline
Applied: Apr 27, 2020
Updated: Dec 13, 2020
📊Site Plan Metrics
#12462785ABC Portal →
FAR:—
Impervious:28.0%
Applied:Apr 27, 2020
Approved:Dec 13, 2020
✅
Approved and Released
Step 5 of 5: Released ✓Site plan fully approved and released. All conditions cleared. Ready for construction permitting.
Next:Pull building permits to begin construction.
📋Scope of Work
The applicant proposes to construct an office building, park pavilion and parking with associated improvements.
📅Entitlement Timeline
Application Filed
+30dApril 27, 2020
In Review
+200dMay 27, 2020
Approved
December 13, 2020
💰Property Tax Assessment
View on TCAD$1.15M
Property Value
Market, Appraised & Assessed values are equal
Land: $7K (1%)Improvements: $1.15M (99%)
📍
Property Address (TCAD)
700 E WELLS BRANCH PKWY 78660
👤
Property Owner (TCAD)
NORTHTOWN MUNICIPAL UTILITY DISTRICT
Year Built:2021
0Tax Year:2026
Type:COMMERCIAL IMPROVED
🤝 Project Team
📝 Applicant Contact
S
Scott Foster
360 Professional Services, Inc.
💰 Fees
Site-Variance/Waiver-Admin Environmental
$249.00
OutstandingTechnology Surcharge-DSD
$9.96
OutstandingEnvironmental Inspection (deposit)
$5,103.00
OutstandingTechnology Surcharge-DSD
$204.12
OutstandingTPW-SP-Administrative Small Site Plan Review
$2,190.00
OutstandingTPW-SP-Site Plan Consolidated ()
$4,380.00
Outstanding-
$4,380.00
OutstandingBasic Notification
$312.00
OutstandingBldg,Prkg & Other Site Work-DSD
$13,054.00
OutstandingUDS Engineering Plan Review
$224.00
OutstandingTechnology Surcharge-DSD
$534.64
OutstandingBasic Notification
$312.00
OutstandingBldg,Prkg & Other Site Work-DSD
$13,054.00
OutstandingUDS Engineering Plan Review
$224.00
OutstandingWPD-Site Plan Wetland Biologist Review
$1,461.00
OutstandingTechnology Surcharge-DSD
$593.08
OutstandingTPW-SP-Site Plan Consolidated
$4,380.00
OutstandingVested Rights Full Determination-DSD
$2,587.00
OutstandingWPD-Chapter 245 Review Determination
$101.00
OutstandingCompleteness Check Fee
$427.00
OutstandingWPD-Site Plan Completeness Check
$34.00
OutstandingTechnology Surcharge-DSD
$125.96
Outstanding📐 Nearby Site Plans
Harris Ridge Business Center Addition
Expired • AUSTIN • Apr 17, 2018
Immanuel 111 Offsite Utility Improvements, Phase 2
Approved and Released • AUSTIN • Jul 10, 2025
Fort Dessau Amenity Center
Approved and Released • AUSTIN • Aug 17, 2015
Harris Ridge Business Center
Approved and Released • AUSTIN • Dec 2, 2014
Harris Ridge Business Center
Expired • AUSTIN • Sep 5, 2014
DESSAU II
Approved and Released • AUSTIN • Mar 2, 2007
Harris Ridge Business Center Addition
Approved and Released • AUSTIN • Aug 13, 2020
HOWARD INDUSTRIAL PARK
Approved • AUSTIN • Jun 19, 2007
DESSAU II HOMES
Approved • AUSTIN • Mar 2, 2007
HOWARD INDUSTRIAL PARK
Approved and Released • AUSTIN • Mar 2, 2007
Harris Ridge Business Center
Expired • AUSTIN • Aug 3, 2020
Parmer 3.1 Office Building
Approved and Released • AUSTIN • Nov 20, 2015
Zoning & Land Use
Current Zoning
N/A
Existing Use
Vacant
Proposed Use
Office/Park
Environmental & Geographic
Watershed ClassSuburban Watershed
🎓 School DistrictPFLUGERVILLE ISD
Impervious Cover28.0%
Case Manager
👤
Randall Rouda
City of Austin Development Services
📌 Case Details
Case Number12462785
Case TypeSite Plan
Sub TypeSite Plan Administrative
Permit NumberSP-2020-0194D
JurisdictionAUSTIN 2 MILE ETJ
TCAD ID0266331003
Property RSN5917616
🔗 Related Cases
Legal Description
LOT 5 BLK E VILLAGE AT NORTHTOWN SEC 3 (PL)