๐ŸProject Closed๐Ÿ”ง Additions to Existing Building๐Ÿ’ต This project is privately funded, on private land for private use.

WILDWOOD UNITED METHODIST CHURCH

8911 FM 1488, Magnolia, TX 77354, Magnolia, TX, 77354
Completed100%

๐Ÿ“ŠProject Metrics

TDLR #EABPRJA9805554
$2.5M
Project Value
โ€”
Square Feet
โ€”
Cost/SqFt
10 months
Duration
Registered:Dec 16, 2008
Start:Jan 1, 2009
Target:Nov 1, 2009
๐Ÿ

Project Closed

Project has been completed and closed

๐Ÿ“‹Scope of Work

Youth Building: classrooms, worship, gym, offices, restrooms, prayer room, cafe. Childrens Bldg.: Calssrooms,

Note: This project is registered under the Texas Accessibility Standards (TAS) program. TDLR registration is required for commercial and public facility construction to ensure compliance with accessibility requirements under Texas Government Code Chapter 469.

๐Ÿ“…Compliance Timeline

Project Registered
December 16, 2008
Construction Start
January 1, 2009
Expected Completion
November 1, 2009