Project has been completed and closed
CP448613 SZB: CNTR TEACH & LEARN 4TH FLR is a Renovation/Alteration project located at 1912 SPEEDWAY 4th Floor, Austin, TX 78705 in Austin, Texas. The project has an estimated value of $581K. UNIVERSITY OF TEXAS AT AUSTIN, THE is the property owner and KOENINGER DESIGN INC. is the design firm of record. The project was registered with TDLR on March 20, 2013.
CP448613 SZB: CNTR TEACH & LEARN 4TH FLR is a renovation/alteration project at 1912 SPEEDWAY 4th Floor, Austin, TX 78705 in Austin, Texas, registered with the Texas Department of Licensing and Regulation (TDLR). Scope of work: RENOVATION OF THE FOURTH FLOOR OF THE GEORGE I. SANCHEZBUILDING.
Construction on CP448613 SZB: CNTR TEACH & LEARN 4TH FLR is complete โ TDLR records show the project passed its required accessibility inspection in Aug 2013. The building is finished and very likely open.
CP448613 SZB: CNTR TEACH & LEARN 4TH FLR is located at 1912 SPEEDWAY 4th Floor, Austin, TX 78705, Austin, TX, 78705, in Travis County.
UNIVERSITY OF TEXAS AT AUSTIN, THE is the property owner/developer of record for CP448613 SZB: CNTR TEACH & LEARN 4TH FLR, per its TDLR project registration.
KOENINGER DESIGN INC. is the design firm of record for CP448613 SZB: CNTR TEACH & LEARN 4TH FLR, according to its TDLR filing.
CP448613 SZB: CNTR TEACH & LEARN 4TH FLR has an estimated construction value of $581K, based on its TDLR filing.
RENOVATION OF THE FOURTH FLOOR OF THE GEORGE I. SANCHEZBUILDING.
Note: This project is registered under the Texas Accessibility Standards (TAS) program. TDLR registration is required for commercial and public facility construction to ensure compliance with accessibility requirements under Texas Government Code Chapter 469.
Filed
Mar 20, 2013
Review Complete
Inspection Complete
Closed
Aug 1, 2013
Building permits found at or near this location
Replacement of complete existing central heat and air system with or without duct work LIKE FOR LIKE: 3 Ton Two Stage Vertical Gas System
Addition of a Manual Transfer Switch and a service disconnect to the building the MTS will be installed after the main service disconnect to provide capabilities to connect a TEMPORARY towable generator when needed during outages. The Manual Transfer Switch is equipped with an interlock mechanism that prevent utility and/or generator power to back feed each other.
New Autofill Pool for 1912 S 3RD ST
45 tunnel below the foundation to replace entire cast iron drain system. 3 access holes - back back front
New Autofill Pool for 1912 S 3RD ST
City of Austin site plan approvals at this location
Active businesses near this construction site
Business data from Google