๐ŸProject Closed๐Ÿ”ง Renovation/Alteration๐Ÿ’ต This project involves public funds, public land, or is a Federally funded roadway project.

MULTIPLE INTERMEDIATE SCHOOL CAMPUS RENO

17400 SATURN LANE, Houston, TX 77058, Houston, TX, 77058
Completed100%

๐Ÿ“ŠProject Metrics

TDLR #EABPRJB6809481
$2.7M
Project Value
โ€”
Square Feet
โ€”
Cost/SqFt
4 months
Duration
Registered:Feb 4, 2016
Start:Mar 1, 2016
Target:Jul 1, 2016
๐Ÿ

Project Closed

Project has been completed and closed

๐Ÿ“‹Scope of Work

Maintenance including sanitary lift station replacement,fire alarm system, high jump and long jump pit refurbis

Note: This project is registered under the Texas Accessibility Standards (TAS) program. TDLR registration is required for commercial and public facility construction to ensure compliance with accessibility requirements under Texas Government Code Chapter 469.

๐Ÿ“…Compliance Timeline

Project Registered
February 4, 2016
Construction Start
March 1, 2016
Expected Completion
July 1, 2016