โœ…Inspection Complete๐Ÿ—๏ธ New Construction๐Ÿ’ต This project involves public funds, public land, or is a Federally funded roadway project.

Northwest Boulevard Improvements

Northwest Boulevard, Georgetown, TX 78626, Georgetown, TX, 78626
Final Inspection85%

๐Ÿ“ŠProject Metrics

TDLR #TABS2019017961
$8.2M
Project Value
386,350
Square Feet
$21/sqft
Cost/SqFt
2 years
Duration
Registered:Aug 8, 2019
Start:Aug 26, 2019
Target:Aug 26, 2021
โœ…

Inspection Complete

Final inspection completed, awaiting project closure

๐Ÿ“‹Scope of Work

2600 LF of 4-lane roadway with a roundabout and intersection improvements, 445 LF of 4-lane bridge over IH-35, pedestrian facilities, utilities, storm water and water quality controls, traffic controls, signage, striping, erosion and sediment control

Note: This project is registered under the Texas Accessibility Standards (TAS) program. TDLR registration is required for commercial and public facility construction to ensure compliance with accessibility requirements under Texas Government Code Chapter 469.

๐Ÿ“…Compliance Timeline

Project Registered
August 8, 2019
Construction Start
August 26, 2019
Expected Completion
August 26, 2021

๐Ÿ“Location & Views

Open in MapsGet Directions|30.65505, -97.67388