Austin Avenue Infrastructure & Pavement (11th St. to 20th St.)
Austin Avenue (11th - 20th Street), Waco, TX 76701, Waco, TX, 76701
Construction50%
๐Project Metrics
TDLR #TABS2020000829$190K
Project Value
270,000
Square Feet
$1/sqft
Cost/SqFt
6 years
Duration
Registered:Sep 13, 2019
Start:Jan 15, 2020
Target:Nov 30, 2025
๐
Review Complete
Design review complete, construction may proceed
๐Scope of Work
The project includes water and sewer utility replacement and a mill and overlay of 270,000 square feet of Austin Avenue between 11th and 20th Streets. Pedestrian improvements along Austin Avenue such as new sidewalk and curb ramps will be included.
Note: This project is registered under the Texas Accessibility Standards (TAS) program. TDLR registration is required for commercial and public facility construction to ensure compliance with accessibility requirements under Texas Government Code Chapter 469.
๐ Compliance Timeline
Project Registered
September 13, 2019
Review Complete
September 13, 2019
Construction Start
January 15, 2020
Expected Completion
November 30, 2025