Fire Station #11 - Storage Shed
7600 Imperial Drive, Waco, TX, 76712
Fire Station #11 - Storage Shed is a new construction project at 7600 Imperial Drive, Waco, in McLennan County, TX, tracked from its Texas Department of Licensing and Regulation (TDLR) registration. Under construction, estimated completion Jan 2027. The project has an estimated value of $150K across about 800 sq ft.
- Estimated project value
- $150K
About this figure
Estimated construction cost supplied in the TDLR filing. This is not a current property appraisal or a final construction invoice.
- Reported floor area
- 800 ft²
About this figure
Square footage reported for this scope of work. It may cover only part of a larger property.
- Estimated cost / ft²
- $188/sqft
About this figure
Calculated from this filing’s estimated cost divided by its reported square footage. Available only when both figures are supplied; it is not a market benchmark.
- Scheduled duration
- 6 months
About this figure
The interval between the filed start and completion dates. These dates describe the proposed schedule and do not measure actual construction progress.
The project record
Project timeline
Explore filed milestones and scheduled dates. Open a milestone for its source.
4 timeline dates shown.
Project registered · TDLR filing
Registration of the project with the Texas Department of Licensing and Regulation.
Source: TDLR filing
View source recordReview complete · TDLR filing
The filing records completion of the accessibility review.
72 days after the preceding date shown.
Source: TDLR filing
View source recordScheduled construction start · Scheduled date
A date supplied in the filing; this does not confirm that work started or finished.
42 days after the preceding date shown.
Source: TDLR filing
View source recordScheduled completion · Scheduled date
A date supplied in the filing; this does not confirm that work started or finished.
183 days after the preceding date shown.
Source: TDLR filing
View source record
📰About Fire Station #11 - Storage Shed
The City of Waco is building a new 800-square-foot storage shed at Fire Station #11, located at 7600 Imperial Drive. This new construction project is registered with TDLR under the specific name Fire Station #11 - Storage Shed. The estimated cost for this facility is $150,000.
Construction on the shed is scheduled to start in August 2026. The project is scheduled to finish in January 2027. This timeline represents a 183-day build window, which is shorter than the 245-day median for new construction filings in McLennan County.
Project Details and Funding
The City of Waco is the owner of record for this development. The project involves public funds and is situated on public land. Rbdr, PLLC is the design firm of record responsible for the plans. Michael Lynn Kelley serves as the registered accessibility specialist for the filing.
The cost per square foot for this shed is $188. This figure is above the county median of $143 per square foot for similar new construction projects. However, the total estimated cost of $150,000 is below the county median of $972,500 for new construction filings in McLennan County.
Regional Context and Status
The City of Waco has six other TDLR-registered projects totaling $33,322,170. These include the Dr. Mae Jackson Development Center and various right-of-way improvements. Rbdr, PLLC has also been involved in six other projects totaling $27,513,730, including work in Waxahachie and Whitney.
The TDLR status for this project is Review Complete, with plan review finished in June 2026. The project was registered in April 2026. The surrounding area, ZIP code 76712, has a population of about 28,719 and a median household income of $96,267 according to U.S. Census estimates.
Review Complete
Design review complete, construction may proceed
Follow this project
Get an email when the status changes — permits pulled, construction started, work finished. Free, and nothing else.
Or watch all projects in 76712 (Waco)
One email per change. Unsubscribe in one click. Privacy.
Fire Station #11 - Storage Shed is a New Construction project located at 7600 Imperial Drive, Waco, TX 76712 in Waco, Texas. The project has an estimated value of $150K covering 800 sq ft. City of Waco is the property owner and RBDR, PLLC is the design firm of record. The project was registered with TDLR on April 9, 2026.
Frequently Asked Questions
When is the storage shed at Fire Station #11 expected to be completed?
Construction is scheduled to finish in January 2027. Work is set to begin in August 2026, creating a 183-day construction period for the 800-square-foot structure.
Who is the design firm for the new Fire Station #11 shed?
Rbdr, PLLC is the design firm of record for this project. They are also involved in other TDLR-registered projects in the region, including facilities in Waxahachie and Whitney.
Is the new storage shed currently open for public use?
The TDLR record indicates the project is in the construction phase. It is scheduled to finish in January 2027, so it is not yet operational or open for use.
What is the estimated cost per square foot for this project?
The estimated cost is $188 per square foot. This is above the McLennan County median of $143 per square foot for new construction filings, though the total project cost is below the county median.
What is Fire Station #11 - Storage Shed?
Fire Station #11 - Storage Shed is a new construction project at 7600 Imperial Drive in Waco, Texas, registered with the Texas Department of Licensing and Regulation (TDLR). Scope of work: New storage shed of approximately 800 square feet for Fire Station #11.
Is Fire Station #11 - Storage Shed open in Waco?
Fire Station #11 - Storage Shed is still under construction in Waco, TX, with an estimated completion of Jan 2027 according to its TDLR registration.
Where is Fire Station #11 - Storage Shed located?
Fire Station #11 - Storage Shed is located at 7600 Imperial Drive, Waco, TX, 76712, in McLennan County.
Who is the owner or developer of Fire Station #11 - Storage Shed?
City of Waco is the property owner/developer of record for Fire Station #11 - Storage Shed, per its TDLR project registration.
Who is the architect or design firm for Fire Station #11 - Storage Shed?
RBDR, PLLC is the design firm of record for Fire Station #11 - Storage Shed, according to its TDLR filing.
How much does Fire Station #11 - Storage Shed cost and how big is it?
Fire Station #11 - Storage Shed has an estimated construction value of $150K and approximately 800 square feet (about $188/sqft), based on its TDLR filing.
Scope of Work
New storage shed of approximately 800 square feet for Fire Station #11.
Note: This project is registered under the Texas Accessibility Standards (TAS) program. TDLR registration is required for commercial and public facility construction to ensure compliance with accessibility requirements under Texas Government Code Chapter 469.
Location & views
7600 Imperial Drive, Waco, TX, 76712
Related Projects
Same Owner
$22.6M totalWatch all construction in 76712 (Waco)
A short email when anything new is filed in this ZIP. One ZIP free, weekly.
Unsubscribe in one click. Privacy.
Keep exploring
What else is changing in Waco?
See the surrounding filings, compare the reported schedules, and follow the places that matter to you.