๐Ÿ“Review Complete๐Ÿ”ง Renovation/Alteration๐Ÿ’ต This project involves public funds, public land, or is a Federally funded roadway project.

Hurricane Harvey Drainage Mitigation Project A-1(Blueridge Ave,Cascade Ave,Wedgewood Ct, Redbud Ln

Blueridge Ave,Cascade Ave,Wedgewood Ct,Redbud Cr, Blueridge Ave,Cascade Ave,Wedgewood Ct,Redbud Cr,, Pasadena, TX 77502, Pasadena, TX, 77502
Construction50%

๐Ÿ“ŠProject Metrics

TDLR #TABS2020011460
$394K
Project Value
65,659
Square Feet
$6/sqft
Cost/SqFt
2 years
Duration
Registered:Feb 13, 2020
Start:Jun 1, 2020
Target:May 31, 2022
๐Ÿ“

Review Complete

Design review complete, construction may proceed

๐Ÿ“‹Scope of Work

Remove and replace existing pavement, improve existing storm drain system and new construction and/or replacement of ex. sidewalks

Note: This project is registered under the Texas Accessibility Standards (TAS) program. TDLR registration is required for commercial and public facility construction to ensure compliance with accessibility requirements under Texas Government Code Chapter 469.

๐Ÿ“…Compliance Timeline

Project Registered
February 13, 2020
Construction Start
June 1, 2020
Expected Completion
May 31, 2022