Hurricane Harvey Drainage Mitigation Project A-4 (Perez Rd,Fenwood Dr,Oaks Dr,Canary Cr,Robin Cr,

Perez Rd,Fenwood Dr,Oaks Dr,Canary Cr,Robin Cr, Perez Rd,Fenwood Dr,Oaks Dr,Canary Cr,Robin Cr,, Pasadena, TX 77502, Pasadena, TX, 77502
Construction50%

๐Ÿ“ŠProject Metrics

TDLR #TABS2020011467
$645K
Project Value
107,451
Square Feet
$6/sqft
Cost/SqFt
2 years
Duration
Registered:Feb 13, 2020
Start:Jun 1, 2020
Target:May 31, 2022
๐Ÿ“

Review Complete

Design review complete, construction may proceed

๐Ÿ“‹Scope of Work

Remove and replace existing pavements, improve existing storm sewer system, and new construction and/or replacement of existing Sidewalks

Note: This project is registered under the Texas Accessibility Standards (TAS) program. TDLR registration is required for commercial and public facility construction to ensure compliance with accessibility requirements under Texas Government Code Chapter 469.

๐Ÿ“…Compliance Timeline

Project Registered
February 13, 2020
Construction Start
June 1, 2020
Expected Completion
May 31, 2022