๐Ÿ“Review Complete๐Ÿ”ง Renovation/Alteration๐Ÿ’ต This project is privately funded, on private land for private use.

David E Morales & Williams Carpenter (392044701)

4131 N. Central Expressway Suite 448, Dallas, TX 75204, Dallas, TX, 75204
Construction50%

๐Ÿ“ŠProject Metrics

TDLR #TABS2020020201
$103K
Project Value
2,097
Square Feet
$49/sqft
Cost/SqFt
2 months
Duration
Registered:Jul 8, 2020
Start:Aug 10, 2020
Target:Oct 5, 2020
๐Ÿ“

Review Complete

Design review complete, construction may proceed

๐Ÿ“‹Scope of Work

Tenant Build-Out

Note: This project is registered under the Texas Accessibility Standards (TAS) program. TDLR registration is required for commercial and public facility construction to ensure compliance with accessibility requirements under Texas Government Code Chapter 469.

๐Ÿ“…Compliance Timeline

Project Registered
July 8, 2020
Construction Start
August 10, 2020
Expected Completion
October 5, 2020