2018 CIP Year 2 - Contract 17
2018 CIP Year 2 - Contract 17 is a renovation/alteration project at None, Fort Worth, in Tarrant County, TX, tracked from its Texas Department of Licensing and Regulation (TDLR) registration. Construction complete (TDLR inspection passed Mar 2022). The project has an estimated value of $1.1M across about 348,480 sq ft.
๐Project Metrics
TDLR #TABS2021000368Project Closed
Project has been completed and closed
2018 CIP Year 2 - Contract 17 is a Renovation/Alteration project located at None, Fort Worth, TX 76104 in Fort Worth, Texas. The project has an estimated value of $1.1M covering 348,480 sq ft. City of Fort Worth is the property owner and Dunaway Associates, LP is the design firm of record. The project was registered with TDLR on September 8, 2020.
โFrequently Asked Questions
What is 2018 CIP Year 2 - Contract 17?
2018 CIP Year 2 - Contract 17 is a renovation/alteration project at None in Fort Worth, Texas, registered with the Texas Department of Licensing and Regulation (TDLR). Scope of work: Reconstruct paving, water, sanitary sewer, and drainage, along with replacing sidewalk segments and ramps
Is 2018 CIP Year 2 - Contract 17 open in Fort Worth?
Construction on 2018 CIP Year 2 - Contract 17 is complete โ TDLR records show the project passed its required accessibility inspection in Mar 2022. The building is finished and very likely open.
Where is 2018 CIP Year 2 - Contract 17 located?
2018 CIP Year 2 - Contract 17 is located at None, Fort Worth, TX, 76104, in Tarrant County.
Who is the owner or developer of 2018 CIP Year 2 - Contract 17?
City of Fort Worth is the property owner/developer of record for 2018 CIP Year 2 - Contract 17, per its TDLR project registration.
Who is the architect or design firm for 2018 CIP Year 2 - Contract 17?
Dunaway Associates, LP is the design firm of record for 2018 CIP Year 2 - Contract 17, according to its TDLR filing.
How much does 2018 CIP Year 2 - Contract 17 cost and how big is it?
2018 CIP Year 2 - Contract 17 has an estimated construction value of $1.1M and approximately 348,480 square feet (about $3/sqft), based on its TDLR filing.
๐Scope of Work
Reconstruct paving, water, sanitary sewer, and drainage, along with replacing sidewalk segments and ramps
Note: This project is registered under the Texas Accessibility Standards (TAS) program. TDLR registration is required for commercial and public facility construction to ensure compliance with accessibility requirements under Texas Government Code Chapter 469.
๐ Compliance Timeline
๐ Project Timeline
Filed
Sep 8, 2020
Review Complete
Inspection Complete
Closed
Mar 31, 2022