Opening ~Dec 2027๐Ÿ“Review Complete๐Ÿ—๏ธ New Construction๐Ÿ’ต This project involves public funds, public land, or is a Federally funded roadway project.

Chalk Hill Trail Phase 1

From Ginger Avenue to Cockrell Hill Road and Illin, Dallas, TX 75211, Dallas, TX, 75211

Chalk Hill Trail Phase 1 is a new construction project at From Ginger Avenue to Cockrell Hill Road and Illin, Dallas, in Dallas County, TX, tracked from its Texas Department of Licensing and Regulation (TDLR) registration. Under construction, estimated completion Dec 2027. The project has an estimated value of $4.0M across about 235,000 sq ft.

Construction50%

๐Ÿ“ŠProject Metrics

TDLR #TABS2021002787
$4.0M
Project Value
235,000
Square Feet
$17/sqft
Cost/SqFt
1y 9mo
Duration
Registered:Oct 19, 2020
Start:Mar 31, 2026
Target:Dec 31, 2027
Remaining:512 days
๐Ÿ“

Review Complete

Design review complete, construction may proceed

Chalk Hill Trail Phase 1 is a New Construction project located at From Ginger Avenue to Cockrell Hill Road and Illin, Dallas, TX 75211 in Dallas, Texas. The project has an estimated value of $4.0M covering 235,000 sq ft. DALLAS COUNTY PLANNING AND DEVELPMENT is the property owner and Arredondo, Zepeda & Brunz, LLC is the design firm of record. The project was registered with TDLR on October 19, 2020.

โ“Frequently Asked Questions

What is Chalk Hill Trail Phase 1?

Chalk Hill Trail Phase 1 is a new construction project at From Ginger Avenue to Cockrell Hill Road and Illin in Dallas, Texas, registered with the Texas Department of Licensing and Regulation (TDLR). Scope of work: Construction of 12-foot wide concrete hike & bike trail, pedestrian bridges, sidewalks, new pedestrian street crossing signal and upgrades to existing traffic signals.

Is Chalk Hill Trail Phase 1 open in Dallas?

Chalk Hill Trail Phase 1 is still under construction in Dallas, TX, with an estimated completion of Dec 2027 according to its TDLR registration.

Where is Chalk Hill Trail Phase 1 located?

Chalk Hill Trail Phase 1 is located at From Ginger Avenue to Cockrell Hill Road and Illin, Dallas, TX, 75211, in Dallas County.

Who is the owner or developer of Chalk Hill Trail Phase 1?

DALLAS COUNTY PLANNING AND DEVELPMENT is the property owner/developer of record for Chalk Hill Trail Phase 1, per its TDLR project registration.

Who is the architect or design firm for Chalk Hill Trail Phase 1?

Arredondo, Zepeda & Brunz, LLC is the design firm of record for Chalk Hill Trail Phase 1, according to its TDLR filing.

How much does Chalk Hill Trail Phase 1 cost and how big is it?

Chalk Hill Trail Phase 1 has an estimated construction value of $4.0M and approximately 235,000 square feet (about $17/sqft), based on its TDLR filing.

๐Ÿ“‹Scope of Work

Construction of 12-foot wide concrete hike & bike trail, pedestrian bridges, sidewalks, new pedestrian street crossing signal and upgrades to existing traffic signals.

Note: This project is registered under the Texas Accessibility Standards (TAS) program. TDLR registration is required for commercial and public facility construction to ensure compliance with accessibility requirements under Texas Government Code Chapter 469.

๐Ÿ“…Compliance Timeline

Project Registered
October 19, 2020
Review Complete
October 19, 2020
Construction Start
March 31, 2026
Expected Completion
December 31, 2027

๐Ÿ“…Project Timeline

Filed

Oct 19, 2020

Review Complete

Oct 19, 2020

Inspection Complete

Closed

๐Ÿ”—Related Projects

Quick Actions

TDLR ID: TABS2021002787
๐Ÿ“Š

Dallas County Economy

3.4%
Unemployment
$399K
Median Listing
12,691
Bldg Permits/yr
8K
Population
7,270
Active Listings
$79K
Median Income
Source: FRED ยท Updated Jun 2026
County projects โ†’

Need a contractor for this project?

Browse verified general contractors active in Dallas County

Find General Contractors in Dallas

Get alerts for Dallas

Daily email when new projects start nearby.

Start Alerts - $19/mo

Download project data

Get curated lists of projects with full contact info.

Browse Data Lists