โœ…Inspection Complete๐Ÿ”ง Renovation/Alteration๐Ÿ’ต This project involves public funds, public land, or is a Federally funded roadway project.

Perry Middle School - Renovation

1709 Beltline Road, Carrollton, TX 75006, Carrollton, TX, 75006
Final Inspection85%

๐Ÿ“ŠProject Metrics

TDLR #TABS2021012337
$33.0M
Project Value
188,929
Square Feet
$175/sqft
Cost/SqFt
1y 6mo
Duration
Registered:Mar 31, 2021
Start:Apr 16, 2021
Target:Oct 14, 2022
โœ…

Inspection Complete

Final inspection completed, awaiting project closure

๐Ÿ“‹Scope of Work

Renovation of 168,421SF and rebuild of 20,508 SF

Note: This project is registered under the Texas Accessibility Standards (TAS) program. TDLR registration is required for commercial and public facility construction to ensure compliance with accessibility requirements under Texas Government Code Chapter 469.

๐Ÿ“…Compliance Timeline

Project Registered
March 31, 2021
Construction Start
April 16, 2021
Expected Completion
October 14, 2022