Project intelligenceTDLR TABS2026000136Additions to Existing Building
Funding type

This project involves public funds, public land, or is a Federally funded roadway project.

Carrollton Elementary School Replacement

1805 Pearl Street, Carrollton, TX, 75006

Opening ~Aug 2027Project Registered

Carrollton Elementary School Replacement is a additions to existing building project at 1805 Pearl Street, Carrollton, in Dallas County, TX, tracked from its Texas Department of Licensing and Regulation (TDLR) registration. Under construction, estimated completion Aug 2027. The project has an estimated value of $49.7M across about 92,250 sq ft.

Estimated project value
$49.7M
About this figure

Estimated construction cost supplied in the TDLR filing. This is not a current property appraisal or a final construction invoice.

Reported floor area
92,250 ft²
About this figure

Square footage reported for this scope of work. It may cover only part of a larger property.

Estimated cost / ft²
$539/sqft
About this figure

Calculated from this filing’s estimated cost divided by its reported square footage. Available only when both figures are supplied; it is not a market benchmark.

Scheduled duration
1y 9mo
About this figure

The interval between the filed start and completion dates. These dates describe the proposed schedule and do not measure actual construction progress.

The project record

Project timeline

Explore filed milestones and scheduled dates. Open a milestone for its source.

Sep 3, 2025726 days across supplied datesAug 30, 2027

3 timeline dates shown.

  1. Project registered · TDLR filing

    Registration of the project with the Texas Department of Licensing and Regulation.

    Source: TDLR filing

    View source record
  2. Scheduled construction start · Scheduled date

    A date supplied in the filing; this does not confirm that work started or finished.

    103 days after the preceding date shown.

    Source: TDLR filing

    View source record
  3. Scheduled completion · Scheduled date

    A date supplied in the filing; this does not confirm that work started or finished.

    623 days after the preceding date shown.

    Source: TDLR filing

    View source record

📰About Carrollton Elementary School Replacement

Carrollton Elementary School Replacement is a new two-story facility planned for 1805 Pearl Street in Carrollton, Texas. The project involves additions to an existing building structure to create a 92,250 sq ft elementary school. This development is registered with TDLR and is targeted for August 2027.

The scope of work includes dedicated classroom spaces, a storm shelter that also functions as a gym, a media center, a cafeteria, and administration areas. A key architectural feature is an interior courtyard designed to provide natural light and an open central space. The total estimated cost for this construction is $49,726,404, which equates to $539 per square foot.

Carrollton-Farmers Branch ISD is the owner of record for this project. Glenn Partners serves as the design firm of record, responsible for the architectural planning. Ronald L Davis is the registered accessibility specialist listed in the filing. The project involves public funds and public land, ensuring it meets specific regulatory standards for public infrastructure.

Project Context and Scale

This filing places the project within a broader pattern of school infrastructure updates in Dallas County. The estimated cost is above the county median for similar additions to existing buildings. The scheduled build window of 623 days is longer than the county median of 182 days for this type of work. The cost per square foot of $539 is also above the county median of $161.

Carrollton-Farmers Branch ISD has six other TDLR-registered projects totaling $127,465,996. These include the replacement of Farmers Branch Elementary School and updates to Newman Smith High School. Glenn Partners has designed six other projects for the district and other entities, totaling $332,548,108. This includes the R.L. Turner High School and Richardson West Middle School projects.

Local coverage has noted the significance of this $49.7 million rebuild for the community. A post on Carrollton Community Voice described the project as replacing one of Carrollton's existing elementary school facilities. A procurement document from Demandstar lists the project under a Construction Manager at Risk process. These third-party references align with the TDLR registration details provided in the official filing.

Project Registered

Project has been registered with TDLR and is in pre-construction phase

Follow this project

Get an email when the status changes — permits pulled, construction started, work finished. Free, and nothing else.

Or watch all projects in 75006 (Carrollton)

One email per change. Unsubscribe in one click. Privacy.

Carrollton Elementary School Replacement is a Additions to Existing Building project located at 1805 Pearl Street, Carrollton, TX 75006 in Carrollton, Texas. The project has an estimated value of $49.7M covering 92,250 sq ft. Carrollton-Farmers Branch ISD is the property owner and Glenn Partners is the design firm of record. The project was registered with TDLR on September 3, 2025.

Frequently Asked Questions

When is the Carrollton Elementary School Replacement scheduled for completion?

The project is registered with TDLR and is targeted for August 2027. Construction start is listed as December 2025, with plan review pending.

Who is the design firm for this school project?

Glenn Partners is the design firm of record. They are responsible for the architectural design of the new 92,250 sq ft facility.

What is the estimated cost of the Carrollton Elementary School Replacement?

The estimated cost is $49,726,404. This figure includes the construction of the new two-story building and associated interior spaces.

Is the school open to the public?

The construction status is registered and targeted for August 2027. The facts provided do not indicate that the school is open or operating.

What specific facilities are included in the new building scope?

The scope includes classroom spaces, a storm shelter/gym, a media center, a cafeteria, administration spaces, and an interior courtyard.

What is Carrollton Elementary School Replacement?

Carrollton Elementary School Replacement is a additions to existing building project at 1805 Pearl Street in Carrollton, Texas, registered with the Texas Department of Licensing and Regulation (TDLR). Scope of work: New two-story 92,250 sf elementary school including classroom spaces, storm shelter/gym, media center, cafeteria, administration spaces, and interior courtyard.

Is Carrollton Elementary School Replacement open in Carrollton?

Carrollton Elementary School Replacement is still under construction in Carrollton, TX, with an estimated completion of Aug 2027 according to its TDLR registration.

Where is Carrollton Elementary School Replacement located?

Carrollton Elementary School Replacement is located at 1805 Pearl Street, Carrollton, TX, 75006, in Dallas County.

Who is the owner or developer of Carrollton Elementary School Replacement?

Carrollton-Farmers Branch ISD is the property owner/developer of record for Carrollton Elementary School Replacement, per its TDLR project registration.

Who is the architect or design firm for Carrollton Elementary School Replacement?

Glenn Partners is the design firm of record for Carrollton Elementary School Replacement, according to its TDLR filing.

How much does Carrollton Elementary School Replacement cost and how big is it?

Carrollton Elementary School Replacement has an estimated construction value of $49.7M and approximately 92,250 square feet (about $539/sqft), based on its TDLR filing.

Scope of Work

New two-story 92,250 sf elementary school including classroom spaces, storm shelter/gym, media center, cafeteria, administration spaces, and interior courtyard.

Note: This project is registered under the Texas Accessibility Standards (TAS) program. TDLR registration is required for commercial and public facility construction to ensure compliance with accessibility requirements under Texas Government Code Chapter 469.

Watch all construction in 75006 (Carrollton)

A short email when anything new is filed in this ZIP. One ZIP free, weekly.

Unsubscribe in one click. Privacy.

Get alerts for Dallas

Daily email when new projects start nearby.

Start Alerts - $19/mo

Download project data

Get curated lists of projects with full contact info.

Browse Data Lists