๐Ÿ“Review Complete๐Ÿ—๏ธ New Construction๐Ÿ’ต This project involves public funds, public land, or is a Federally funded roadway project.

Chris Andrews Boat Ramp

115 U.S. 181, Portland, TX 78374, Portland, TX, 78374
Construction50%

๐Ÿ“ŠProject Metrics

TDLR #TABS2021023055
$750K
Project Value
40,000
Square Feet
$19/sqft
Cost/SqFt
4 months
Duration
Registered:Aug 27, 2021
Start:Dec 1, 2021
Target:Apr 1, 2022
๐Ÿ“

Review Complete

Design review complete, construction may proceed

๐Ÿ“‹Scope of Work

Construction of boat ramp and parking lot.

Note: This project is registered under the Texas Accessibility Standards (TAS) program. TDLR registration is required for commercial and public facility construction to ensure compliance with accessibility requirements under Texas Government Code Chapter 469.

๐Ÿ“…Compliance Timeline

Project Registered
August 27, 2021
Construction Start
December 1, 2021
Expected Completion
April 1, 2022