โœ…Inspection Complete๐Ÿ”ง Renovation/Alteration๐Ÿ’ต This project involves public funds, public land, or is a Federally funded roadway project.

Cimarron Secs 2,3,4 and 5 Subdivision Drainage Improvements - 2018

Intersection of Indian Ridge Dr and Cooper Creek Dr. to Intersection of Red Rock Canyon Dr., Katy, TX 77450, Katy, TX, 77450
Final Inspection85%

๐Ÿ“ŠProject Metrics

TDLR #TABS2022011095
$8.7M
Project Value
38,430
Square Feet
$226/sqft
Cost/SqFt
1y 9mo
Duration
Registered:Feb 7, 2022
Start:Apr 1, 2022
Target:Jan 2, 2024
โœ…

Inspection Complete

Final inspection completed, awaiting project closure

๐Ÿ“‹Scope of Work

Construct of approximately 8,025 linear feet of reinforced concrete pipe, reinforced concrete box, inlets, manholes, junction boxes and culvert to provide more capacity to the storm sewer system.

Note: This project is registered under the Texas Accessibility Standards (TAS) program. TDLR registration is required for commercial and public facility construction to ensure compliance with accessibility requirements under Texas Government Code Chapter 469.

๐Ÿ“…Compliance Timeline

Project Registered
February 7, 2022
Construction Start
April 1, 2022
Expected Completion
January 2, 2024