Project intelligenceTDLR TABS2026016911Renovation/Alteration
Funding type

This project involves public funds, public land, or is a Federally funded roadway project.

Memorial Parkway Subdivision Drainage Improvements in Houston, TX

Park Bend Drive to Highland Knolls Drive, Houston, TX, 77450

Opening ~Feb 2027Review Complete

Memorial Parkway Subdivision Drainage Improvements is a renovation/alteration project at Park Bend Drive to Highland Knolls Drive, Houston, in Harris County, TX, tracked from its Texas Department of Licensing and Regulation (TDLR) registration. Under construction, estimated completion Feb 2027. The project has an estimated value of $4.5M across about 6,180 sq ft.

Estimated project value
$4.5M
About this figure

Estimated construction cost supplied in the TDLR filing. This is not a current property appraisal or a final construction invoice.

Reported floor area
6,180 ft²
About this figure

Square footage reported for this scope of work. It may cover only part of a larger property.

Estimated cost / ft²
$730/sqft
About this figure

Calculated from this filing’s estimated cost divided by its reported square footage. Available only when both figures are supplied; it is not a market benchmark.

Scheduled duration
7 months
About this figure

The interval between the filed start and completion dates. These dates describe the proposed schedule and do not measure actual construction progress.

Explore the linked construction record and source history

The project record

Project timeline

Explore filed milestones and scheduled dates. Open a milestone for its source.

Apr 6, 2026301 days across supplied datesFeb 1, 2027

4 timeline dates shown.

  1. Project registered · TDLR filing

    Registration of the project with the Texas Department of Licensing and Regulation.

    Source: TDLR filing

    View source record
  2. Review complete · TDLR filing

    The filing records completion of the accessibility review.

    4 days after the preceding date shown.

    Source: TDLR filing

    View source record
  3. Scheduled construction start · Scheduled date

    A date supplied in the filing; this does not confirm that work started or finished.

    94 days after the preceding date shown.

    Source: TDLR filing

    View source record
  4. Scheduled completion · Scheduled date

    A date supplied in the filing; this does not confirm that work started or finished.

    203 days after the preceding date shown.

    Source: TDLR filing

    View source record

📰About Memorial Parkway Subdivision Drainage Improvements

Harris County is undertaking a major drainage upgrade along Park Bend Drive and Highland Knolls Drive in Houston. The project, valued at $4,510,651, involves the renovation and alteration of existing infrastructure to improve stormwater management. This specific work zone covers 6,180 square feet of roadway and sidewalk replacement within the Memorial Parkway Subdivision.

BGE, Inc. serves as the design firm of record for this initiative. The scope includes upgrading the existing storm sewer collection system and adding new capacity to handle runoff. Concurrently, the project replaces aging roadway surfaces and sidewalks to ensure structural integrity and accessibility compliance. The registered accessibility specialist for the filing is Robert W Green.

Project Timeline and Status

TDLR completed plan review in April 2026 and construction is scheduled to finish in February 2027, with work starting July 2026. The project is registered with the Texas Department of Licensing and Regulation under the TABS program, ensuring that accessibility standards are met during the renovation process. The estimated construction window spans approximately 203 days, which is longer than the 92-day median build window for similar renovation projects in Harris County.

The estimated cost of $4,510,651 places this project in the top quarter of renovation and alteration filings in Harris County. The cost per square foot is $730, significantly above the county median of $80 per square foot for this project type. This higher cost reflects the complexity of integrating storm sewer upgrades with surface infrastructure improvements in an established residential area. The project involves public funds and is located on public land, underscoring its importance to the local community.

The neighborhood surrounding the work site includes several local businesses and amenities. Residents and commuters in the 77450 ZIP code, which has a median household income of $105,607, will experience temporary disruptions during the construction phase. The area is characterized by owner-occupied housing, with a median home value of $342,000. Local entities such as El Jarrito and Handyman Home Solutions operate nearby, indicating an active commercial and residential mix in the vicinity.

BGE, Inc. has a track record of managing large-scale infrastructure projects across Texas. Other registered projects by this firm include the Rudeloff Road project in Seguin and the Harris County W.C.I.D. No. 157 in Cypress. The Memorial Parkway Subdivision Drainage Improvements project aligns with the firm’s expertise in civil engineering and public works. The completion of this project will enhance the resilience of the local drainage system, reducing the risk of flooding and improving overall road conditions for drivers and pedestrians in the Memorial Parkway area.

Review Complete

Design review complete, construction may proceed

Follow this project

Get an email when the status changes — permits pulled, construction started, work finished. Free, and nothing else.

Or watch all projects in 77450 (Houston)

One email per change. Unsubscribe in one click. Privacy.

Memorial Parkway Subdivision Drainage Improvements is a Renovation/Alteration project located at Park Bend Drive to Highland Knolls Drive, Houston, TX 77450 in Houston, Texas. The project has an estimated value of $4.5M covering 6,180 sq ft. Harris County - Office of County Engineer is the property owner and BGE, Inc. is the design firm of record. The project was registered with TDLR on April 6, 2026.

Frequently Asked Questions

When will construction start?

Construction is scheduled to begin in July 2026, following the completion of plan review in April 2026.

Who is the design firm?

BGE, Inc. is the design firm of record for this drainage improvement project.

Is the project open to the public?

The project is in the planning and construction phase. It is not a business opening, but a public infrastructure improvement.

What is the scope of work?

The scope includes upgrading the storm sewer collection system and replacing roadway and sidewalks.

What is Memorial Parkway Subdivision Drainage Improvements?

Memorial Parkway Subdivision Drainage Improvements is a renovation/alteration project at Park Bend Drive to Highland Knolls Drive in Houston, Texas, registered with the Texas Department of Licensing and Regulation (TDLR). Scope of work: Upgrade and addition to existing storm sewer collection system. Roadway and sidewalks will be replaced.

Is Memorial Parkway Subdivision Drainage Improvements open in Houston?

Memorial Parkway Subdivision Drainage Improvements is still under construction in Houston, TX, with an estimated completion of Feb 2027 according to its TDLR registration.

Where is Memorial Parkway Subdivision Drainage Improvements located?

Memorial Parkway Subdivision Drainage Improvements is located at Park Bend Drive to Highland Knolls Drive, Houston, TX, 77450, in Harris County.

Who is the owner or developer of Memorial Parkway Subdivision Drainage Improvements?

Harris County - Office of County Engineer is the property owner/developer of record for Memorial Parkway Subdivision Drainage Improvements, per its TDLR project registration.

Who is the architect or design firm for Memorial Parkway Subdivision Drainage Improvements?

BGE, Inc. is the design firm of record for Memorial Parkway Subdivision Drainage Improvements, according to its TDLR filing.

How much does Memorial Parkway Subdivision Drainage Improvements cost and how big is it?

Memorial Parkway Subdivision Drainage Improvements has an estimated construction value of $4.5M and approximately 6,180 square feet (about $730/sqft), based on its TDLR filing.

Scope of Work

Upgrade and addition to existing storm sewer collection system. Roadway and sidewalks will be replaced.

Note: This project is registered under the Texas Accessibility Standards (TAS) program. TDLR registration is required for commercial and public facility construction to ensure compliance with accessibility requirements under Texas Government Code Chapter 469.

Location & views

Park Bend Drive to Highland Knolls Drive, Houston, TX, 77450

Explore the supplied address

A precise map point has not been loaded. Choose to look up the address, or open it in Google Maps using the link below.

Location by street address

Watch all construction in 77450 (Houston)

A short email when anything new is filed in this ZIP. One ZIP free, weekly.

Unsubscribe in one click. Privacy.