๐Project Registered๐๏ธ New Construction๐ต This project involves public funds, public land, or is a Federally funded roadway project.
US 271 Phase 3 (CSJ: 3290-02-009, etc.)
Various Locations, Gladewater, TX 75647, Gladewater, TX, 75647
Pre-Construction15%
๐Project Metrics
TDLR #TABS2026011492$949K
Project Value
75,000
Square Feet
$13/sqft
Cost/SqFt
3y 1mo
Duration
Registered:Feb 2, 2026
Start:Apr 28, 2028
Target:Apr 28, 2031
Remaining:1891 days
๐
Project Registered
Project has been registered with TDLR and is in pre-construction phase
๐Scope of Work
Widen from 2 lanes to 4 lanes with median, shared use path, sidewalks, ADA curb ramps, crosswalks and pedestrian signals.
Note: This project is registered under the Texas Accessibility Standards (TAS) program. TDLR registration is required for commercial and public facility construction to ensure compliance with accessibility requirements under Texas Government Code Chapter 469.
๐ Compliance Timeline
Project Registered
February 2, 2026
Construction Start
April 28, 2028
Expected Completion
April 28, 2031
๐Related Projects
๐คSame Owner
$4.3M total๐๏ธSame Design Firm
$4.3M totalProperty Owner
๐ค
TxDOT District: Tyler
4 projects ยท $4.3M
View all projects
2709 W. Front St., Tyler, Texas 75702
Design Firm
๐๏ธ
BGE, Inc.
4 projects ยท $4.3M
View all projects
10777 Westheimer, Suite 400, Houston, Texas 77042