US 271 Phase 3 (CSJ: 3290-02-009, etc.) in Gladewater, TX

Various Locations, Gladewater, TX, 75647

Opening ~Apr 2031Review Complete

US 271 Phase 3 (CSJ: 3290-02-009, etc.) is a new construction project at Various Locations, Gladewater, in Upshur County, TX, tracked from its Texas Department of Licensing and Regulation (TDLR) registration. Under construction, estimated completion Apr 2031. The project has an estimated value of $949K across about 75,000 sq ft.

Estimated project value
$949K
About this figure

Estimated construction cost supplied in the TDLR filing. This is not a current property appraisal or a final construction invoice.

Reported floor area
75,000 ft²
About this figure

Square footage reported for this scope of work. It may cover only part of a larger property.

Estimated cost / ft²
$13/sqft
About this figure

Calculated from this filing’s estimated cost divided by its reported square footage. Available only when both figures are supplied; it is not a market benchmark.

Scheduled duration
3y 1mo
About this figure

The interval between the filed start and completion dates. These dates describe the proposed schedule and do not measure actual construction progress.

The project record

Project timeline

Explore filed milestones and scheduled dates. Open a milestone for its source.

Feb 2, 20261,911 days across supplied datesApr 28, 2031

4 timeline dates shown.

  1. Project registered · TDLR filing

    Registration of the project with the Texas Department of Licensing and Regulation.

    Source: TDLR filing

    View source record
  2. Review complete · TDLR filing

    The filing records completion of the accessibility review.

    25 days after the preceding date shown.

    Source: TDLR filing

    View source record
  3. Scheduled construction start · Scheduled date

    A date supplied in the filing; this does not confirm that work started or finished.

    791 days after the preceding date shown.

    Source: TDLR filing

    View source record
  4. Scheduled completion · Scheduled date

    A date supplied in the filing; this does not confirm that work started or finished.

    1,095 days after the preceding date shown.

    Source: TDLR filing

    View source record

📰About US 271 Phase 3 (CSJ: 3290-02-009, etc.)

US 271 Phase 3 (CSJ: 3290-02-009, etc.) is a new construction project in Gladewater, Texas, that will widen the roadway from two lanes to four lanes with a median. The filing identifies the work as including a shared use path, sidewalks, ADA curb ramps, crosswalks, and pedestrian signals. The project spans various locations in Upshur County and is estimated to cover 75,000 sq ft of construction area.

The estimated cost for this infrastructure improvement is $948,782. This figure places the project’s cost close to the county median for new construction filings in Upshur County, which stands at $850,000. However, the calculated cost per square foot is $13, which is below the county median of $182 per square foot. This low per-square-foot cost is typical for linear roadway projects where the square footage represents the length and width of the pavement and related infrastructure rather than a building footprint.

Project Scope and Administration

TxDOT District: Tyler is the owner of record for this Federally funded roadway project. BGE, Inc. serves as the design firm of record, having previously worked on several other TDLR-registered projects in Texas. Frank Fonseca is the registered accessibility specialist listed in the filing. The project is registered with TDLR, and plan review was completed in February 2026. The TDLR status is listed as Review Complete.

Construction is scheduled to start in April 2028 and is scheduled to finish in April 2031. This scheduled build window of 1095 days is longer than the county median of 183 days for similar filings, reflecting the complexity and scale of widening a major state highway.

Gladewater, with a population of about 13,457 according to U.S. Census ACS 2023 five-year estimates for ZIP 75647, is a predominantly owner-occupied community. The median household income in the area is $61,356, and the median owner-occupied home value is $164,300. This project aims to improve transportation infrastructure and accessibility for residents and travelers in this Upshur County location.

Review Complete

Design review complete, construction may proceed

Follow this project

Get an email when the status changes — permits pulled, construction started, work finished. Free, and nothing else.

Or watch all projects in 75647 (Gladewater)

One email per change. Unsubscribe in one click. Privacy.

US 271 Phase 3 (CSJ: 3290-02-009, etc.) is a New Construction project located at Various Locations, Gladewater, TX 75647 in Gladewater, Texas. The project has an estimated value of $949K covering 75,000 sq ft. TxDOT District: Tyler is the property owner and BGE, Inc. is the design firm of record. The project was registered with TDLR on February 2, 2026.

Frequently Asked Questions

When is construction scheduled to finish?

The project is scheduled to finish in April 2031, with construction beginning in April 2028.

What is the estimated cost of the project?

The estimated cost is $948,782, which is close to the Upshur County median for new construction.

Who is the owner of record?

TxDOT District: Tyler is the owner of record for this Federally funded roadway project.

What specific improvements are included in the scope?

The scope includes widening from 2 to 4 lanes with a median, shared use paths, sidewalks, ADA curb ramps, crosswalks, and pedestrian signals.

Is the project currently open to the public?

The TDLR record indicates construction is scheduled to start in April 2028, so the project is not yet open or operating.

What is US 271 Phase 3 (CSJ: 3290-02-009, etc.)?

US 271 Phase 3 (CSJ: 3290-02-009, etc.) is a new construction project at Various Locations in Gladewater, Texas, registered with the Texas Department of Licensing and Regulation (TDLR). Scope of work: Widen from 2 lanes to 4 lanes with median, shared use path, sidewalks, ADA curb ramps, crosswalks and pedestrian signals.

Is US 271 Phase 3 (CSJ: 3290-02-009, etc.) open in Gladewater?

US 271 Phase 3 (CSJ: 3290-02-009, etc.) is still under construction in Gladewater, TX, with an estimated completion of Apr 2031 according to its TDLR registration.

Where is US 271 Phase 3 (CSJ: 3290-02-009, etc.) located?

US 271 Phase 3 (CSJ: 3290-02-009, etc.) is located at Various Locations, Gladewater, TX, 75647, in Upshur County.

Who is the owner or developer of US 271 Phase 3 (CSJ: 3290-02-009, etc.)?

TxDOT District: Tyler is the property owner/developer of record for US 271 Phase 3 (CSJ: 3290-02-009, etc.), per its TDLR project registration.

Who is the architect or design firm for US 271 Phase 3 (CSJ: 3290-02-009, etc.)?

BGE, Inc. is the design firm of record for US 271 Phase 3 (CSJ: 3290-02-009, etc.), according to its TDLR filing.

How much does US 271 Phase 3 (CSJ: 3290-02-009, etc.) cost and how big is it?

US 271 Phase 3 (CSJ: 3290-02-009, etc.) has an estimated construction value of $949K and approximately 75,000 square feet (about $13/sqft), based on its TDLR filing.

Scope of Work

Widen from 2 lanes to 4 lanes with median, shared use path, sidewalks, ADA curb ramps, crosswalks and pedestrian signals.

Note: This project is registered under the Texas Accessibility Standards (TAS) program. TDLR registration is required for commercial and public facility construction to ensure compliance with accessibility requirements under Texas Government Code Chapter 469.

Location & views

Various Locations, Gladewater, TX, 75647

Loading location map…
32.53653, -94.94272

Watch all construction in 75647 (Gladewater)

A short email when anything new is filed in this ZIP. One ZIP free, weekly.

Unsubscribe in one click. Privacy.

Keep exploring

What else is changing in Gladewater?

See the surrounding filings, compare the reported schedules, and follow the places that matter to you.