๐Ÿ“Review Complete๐Ÿ—๏ธ New Construction๐Ÿ’ต This project involves public funds, public land, or is a Federally funded roadway project.

Portwall Street - Sidewalk 2020

200 Portwall Street, Houston, TX 77029, Houston, TX, 77029
Construction50%

๐Ÿ“ŠProject Metrics

TDLR #TABS2022019183
$166K
Project Value
8,000
Square Feet
$21/sqft
Cost/SqFt
6y 3mo
Duration
Registered:May 17, 2022
Start:Jul 1, 2022
Target:Sep 1, 2028
Remaining:980 days
๐Ÿ“

Review Complete

Design review complete, construction may proceed

๐Ÿ“‹Scope of Work

10 ft. sidewalk

Note: This project is registered under the Texas Accessibility Standards (TAS) program. TDLR registration is required for commercial and public facility construction to ensure compliance with accessibility requirements under Texas Government Code Chapter 469.

๐Ÿ“…Compliance Timeline

Project Registered
May 17, 2022
Construction Start
July 1, 2022
Expected Completion
September 1, 2028