๐Review Complete๐๏ธ New Construction๐ต This project involves public funds, public land, or is a Federally funded roadway project.
Conroe Firestation No.8
676 FM 3083, Conroe, TX 77301, Conroe, TX, 77301
Construction50%
๐Project Metrics
TDLR #TABS2023014956$7.0M
Project Value
11,063
Square Feet
$633/sqft
Cost/SqFt
3y 6mo
Duration
Registered:Mar 24, 2023
Start:May 1, 2023
Target:Oct 1, 2026
Remaining:278 days
๐
Review Complete
Design review complete, construction may proceed
๐Scope of Work
New 3 Bay Firestation
Note: This project is registered under the Texas Accessibility Standards (TAS) program. TDLR registration is required for commercial and public facility construction to ensure compliance with accessibility requirements under Texas Government Code Chapter 469.
๐ Compliance Timeline
Project Registered
March 24, 2023
Construction Start
May 1, 2023
Expected Completion
October 1, 2026
๐Related Projects
๐คSame Owner
$5.4M totalProperty Owner
๐ค
City of Conroe
4 projects ยท $5.4M
View all projects
300 West Davis, Conroe, Texas 77301
Design Firm
๐๏ธ
PGAL
4 projects ยท $16.0M
View all projects
3131 Briarpark Dr #200, Houston, Texas 77042
Tenant
๐ข
Ken Kreger