PISD 2023 HVAC and Control System Renovations
Multiple Campuses within PISD Administration = 1401D W Pecan (no work here), Pflugerville, TX 78660, Pflugerville, TX, 78660
Construction50%
๐Project Metrics
TDLR #TABS2023025861$2.1M
Project Value
3,000
Square Feet
$716/sqft
Cost/SqFt
11 months
Duration
Registered:Aug 15, 2023
Start:Oct 2, 2023
Target:Aug 31, 2024
๐
Review Complete
Design review complete, construction may proceed
๐Scope of Work
Replacement of HVAC Units / Upgrades to two control systems / replacement of three Kitchen Hoods / Overhead door replacement
Note: This project is registered under the Texas Accessibility Standards (TAS) program. TDLR registration is required for commercial and public facility construction to ensure compliance with accessibility requirements under Texas Government Code Chapter 469.
๐ Compliance Timeline
Project Registered
August 15, 2023
Construction Start
October 2, 2023
Expected Completion
August 31, 2024
๐Related Projects
๐คSame Owner
$77.5M total๐๏ธSame Design Firm
$2.5M totalProperty Owner
๐ค
Pflugerville ISD
Contact: Robert Sands
4 projects ยท $77.5M
View all projects
2021 Crystal Bend Drive, Pflugerville, Texas 78660
Design Firm
๐๏ธ
ESA Energy Systems Associates, Inc.
3 projects ยท $2.5M
View all projects
432 Monahans Drive, Georgetown, Texas 78628