๐Review Complete๐๏ธ New Construction๐ต This project involves public funds, public land, or is a Federally funded roadway project.
South Pea Ridge and Hogan Road Improvements
South Pea Ridge & Hogan Road, Temple, TX 76501, Temple, TX, 76501
Construction50%
๐Project Metrics
TDLR #TABS2024010652$5.7M
Project Value
80,026
Square Feet
$71/sqft
Cost/SqFt
2y 1mo
Duration
Registered:Feb 1, 2024
Start:Mar 1, 2024
Target:Mar 6, 2026
Remaining:64 days
๐
Review Complete
Design review complete, construction may proceed
๐Scope of Work
Reconstruction of South Pea Ridge Rd. to Westwood Hills Blvd., and Hogan Rd. from Westwood Hills Blvd. to South Pea Ridge Rd., consisting of road reconstruction, curb and gutter, sidewalk, drainage, signing, and pavement markings. 80,026sf
Note: This project is registered under the Texas Accessibility Standards (TAS) program. TDLR registration is required for commercial and public facility construction to ensure compliance with accessibility requirements under Texas Government Code Chapter 469.
๐ Compliance Timeline
Project Registered
February 1, 2024
Review Complete
February 1, 2024
Construction Start
March 1, 2024
Expected Completion
March 6, 2026
๐Related Projects
Property Owner
๐ค
City of Temple - Public Works
Contact: Deborah Mason, PE
View company profile
3210 E. Ave. H, Bldg. A, Ste. 130, Temple, Texas 76501
Design Firm
๐๏ธ
Kimley-Horn
4 projects ยท $40.0M
View all projects
10814 Jollyville Road, Campus IV, Ste. 200, Austin, Texas 78759