๐Project Registered๐ง Renovation/Alteration๐ต This project involves public funds, public land, or is a Federally funded roadway project.
FBISD BP036 Sitework Package 1
7007 KNIGHTS CT, Missouri City, TX 77459, Missouri City, TX, 77459
Pre-Construction15%
๐Project Metrics
TDLR #TABS2026012078$1.2M
Project Value
1,000
Square Feet
$1.20K/sqft
Cost/SqFt
7 months
Duration
Registered:Feb 9, 2026
Start:May 31, 2026
Target:Dec 30, 2026
Remaining:311 days
๐
Project Registered
Project has been registered with TDLR and is in pre-construction phase
๐Scope of Work
SCOPE OF WORK: 1. REPLACE EXISTING COVERED WALKWAY AND COURTYARD CANOPY COVERING TO PROPERLY DRAIN AND JET CLEAN EXISTING STORM LINE. (SID36005) 2. REPLACE EXISTING SKYLIGHT SYSTEM. (SID36011) 3. REMOVE, REGRADE, AND REPLACE CONCRETE PAVEMENT THAT HA
Note: This project is registered under the Texas Accessibility Standards (TAS) program. TDLR registration is required for commercial and public facility construction to ensure compliance with accessibility requirements under Texas Government Code Chapter 469.
๐ Compliance Timeline
Project Registered
February 9, 2026
Construction Start
May 31, 2026
Expected Completion
December 30, 2026
๐Related Projects
๐คSame Owner
$3.5M total๐Nearby Projects
Within 1 kmProperty Owner
๐ค
FBISD Design and Construction Department
4 projects ยท $3.5M
View all projects
2323 Texas Parkway, Missouri City, Texas 77489
Design Firm
๐๏ธ
MWA Architects
4 projects ยท $3.5M
View all projects
11767 Katy Freeway 430, Houston, Texas 77079