Permitted

South Ridge Industrial

2740 Almeda Genoa Rd, Houston, TX 77007, Houston (Harris County)

TDLR Project: 3

Source coverage

3 linked records

Explore the filings behind this project.

How these records are linked

Record matching confidence: 65%. This describes the record association, not construction completion.

Reported project value
$9.0M
About this figure

The value recorded for this linked project. Filings may describe overlapping scopes, so this is not a final invoice or an appraisal.

Reported floor area
Not supplied
About this figure

Floor area associated with the linked project record. Open the source records to inspect each reported scope.

Site area
Not supplied
About this figure

The count or area provided by the linked records. Proposed figures may change as plans are revised.

Last recorded activity
Oct 1, 2026
About this figure

The latest activity date in this linked project record. It does not establish current work at the site.

The project record

Project timeline

Explore filed milestones and scheduled dates. Open a milestone for its source.

Oct 1, 2026305 days across supplied datesAug 2, 2027

9 timeline dates shown.

  1. TDLR Project: South Ridge Industrial · TDLR Project · TABS2027002537

    Project Registered

    Source: TDLR Project · TABS2027002537

    View source record
  2. TDLR Project: South Ridge Industrial · TDLR Project · TABS2027002535

    Project Registered

    Same day as the preceding date shown.

    Source: TDLR Project · TABS2027002535

    View source record
  3. TDLR Project: South Ridge Industrial · TDLR Project · TABS2027002538

    Project Registered

    Same day as the preceding date shown.

    Source: TDLR Project · TABS2027002538

    View source record
  4. Construction Start · Scheduled date

    Projected start

    A date supplied in the filing; this does not confirm that work started or finished.

    95 days after the preceding date shown.

    Source: TDLR Project · TABS2027002537

    View source record
  5. Construction Start · Scheduled date

    Projected start

    A date supplied in the filing; this does not confirm that work started or finished.

    Same day as the preceding date shown.

    Source: TDLR Project · TABS2027002535

    View source record
  6. Construction Start · Scheduled date

    Projected start

    A date supplied in the filing; this does not confirm that work started or finished.

    Same day as the preceding date shown.

    Source: TDLR Project · TABS2027002538

    View source record
Show 3 more dates
  1. Expected Completion · Scheduled date

    Projected completion

    A date supplied in the filing; this does not confirm that work started or finished.

    210 days after the preceding date shown.

    Source: TDLR Project · TABS2027002537

    View source record
  2. Expected Completion · Scheduled date

    Projected completion

    A date supplied in the filing; this does not confirm that work started or finished.

    Same day as the preceding date shown.

    Source: TDLR Project · TABS2027002535

    View source record
  3. Expected Completion · Scheduled date

    Projected completion

    A date supplied in the filing; this does not confirm that work started or finished.

    Same day as the preceding date shown.

    Source: TDLR Project · TABS2027002538

    View source record

Project Metrics

TDLR #TABS2027002537
$9.0M
Total Value
Started:Oct 1, 2026
Last activity:Oct 1, 2026
Duration:—

Location & views

2740 Almeda Genoa Rd, Houston, TX 77007

29.61404, -95.38179
Detailed source chronology
2026
Oct 1
10 days ago
TDLR Project: South Ridge Industrial
TDLR Project • Project Registered
Valuation: $2.5M
Link confidence: 100%
Open record
October 1, 2026
TABS2027002537
2026
Oct 1
10 days ago
TDLR Project: South Ridge Industrial
TDLR Project • Project Registered
Valuation: $4.1M
Link confidence: 100%
Open record
October 1, 2026
TABS2027002535
2026
Oct 1
10 days ago
TDLR Project: South Ridge Industrial
TDLR Project • Project Registered
Valuation: $2.5M
Link confidence: 100%
Open record
October 1, 2026
TABS2027002538
2027
Jan 4
3 mos from now
Construction Start
TDLR Project • Projected start
Work itemSouth Ridge Industrial
Start Jan 4, 2027→End Aug 2, 2027
Open record
January 4, 2027
TABS2027002537
2027
Jan 4
3 mos from now
Construction Start
TDLR Project • Projected start
Work itemSouth Ridge Industrial
Start Jan 4, 2027→End Aug 2, 2027
Open record
January 4, 2027
TABS2027002535
2027
Jan 4
3 mos from now
Construction Start
TDLR Project • Projected start
Work itemSouth Ridge Industrial
Start Jan 4, 2027→End Aug 2, 2027
Open record
January 4, 2027
TABS2027002538
2027
Aug 2
10 mos from now
Expected Completion
TDLR Project • Projected completion
Work itemSouth Ridge Industrial
Start Jan 4, 2027→End Aug 2, 2027
Open record
August 2, 2027
TABS2027002537
2027
Aug 2
10 mos from now
Expected Completion
TDLR Project • Projected completion
Work itemSouth Ridge Industrial
Start Jan 4, 2027→End Aug 2, 2027
Open record
August 2, 2027
TABS2027002535
2027
Aug 2
10 mos from now
Expected Completion
TDLR Project • Projected completion
Work itemSouth Ridge Industrial
Start Jan 4, 2027→End Aug 2, 2027
Open record
August 2, 2027
TABS2027002538

Linked records by source

TDLR Projects (3)

Public source records
South Ridge Industrial
Project Registered • Oct 1, 2026
TABS2027002537
Description: New speculative ground up 25,000sf warehouse building to serve as a light manufacturing, storage and office
Facility: Building 2
Design firm: Method Architecture
Estimated cost: $2.5M
Sq Ft: 25,000
South Ridge Industrial
Project Registered • Oct 1, 2026
TABS2027002535
Description: New speculative ground up 41,160sf industrial warehouse building to serve as light manufacturing, storage and office
Facility: Building 1
Design firm: Method Architecture
Estimated cost: $4.1M
Sq Ft: 41,160
South Ridge Industrial
Project Registered • Oct 1, 2026
TABS2027002538
Description: New speculative groundup 25,000sf industrial warehouse building to serve as light manufacturing storage and office
Facility: Building 3
Design firm: Method Architecture
Estimated cost: $2.5M
Sq Ft: 25,000