Construction intelligence · Linked public records
Removal of thirteen corroded steel trusses. The existing roof will need to be removed to decommission the corroded steel trusses. Installation of thirteen new steel trusses with an Epoxy Novolac Coating to protect it from water chemical soaps and moisture. The new roof will transition with the existing roof construction aligned with existing parapet walls and maintain a weathertight building envelope.
2910 E 5TH ST, Austin (Travis County)
Source coverage
5 linked records
Explore the filings behind this project.
How these records are linked
Record matching confidence: 75%. This describes the record association, not construction completion.
- Reported project value
- $293K
About this figure
The value recorded for this linked project. Filings may describe overlapping scopes, so this is not a final invoice or an appraisal.
- Reported floor area
- Not supplied
About this figure
Floor area associated with the linked project record. Open the source records to inspect each reported scope.
- Site area
- Not supplied
About this figure
The count or area provided by the linked records. Proposed figures may change as plans are revised.
- Last recorded activity
- Nov 20, 2026
About this figure
The latest activity date in this linked project record. It does not establish current work at the site.
The project record
Project timeline
Explore filed milestones and scheduled dates. Open a milestone for its source.
7 timeline dates shown.
Permit 2026-100761 BP: Removal of thirteen corroded steel trusses. The existing roof will need to be removed to decommission the corroded steel trusses. Installation of thirteen new steel trusses with an Epoxy Novolac Coating to protect it from water chemical soaps and moisture. The new roof will transition with the existing roof construction aligned with existing parapet walls and maintain a weathertight building envelope. · Building Permit · 2026-100761 BP
Permit 2026-112554 BP: Remove existing PVC and fanfold cover board down to original BUR mechanically attach fan fold and 50mil single-ply PVC membrane 1 Admin · Building Permit · 2026-112554 BP
Active
29 days after the preceding date shown.
Source: Building Permit · 2026-112554 BP
View source recordPermit 2026-112767 BP: Remove existing PVC and fanfold cover board down to original BUR mechanically attach fan fold and 50mil single-ply PVC. 2 FLEET · Building Permit · 2026-112767 BP
Active
Same day as the preceding date shown.
Source: Building Permit · 2026-112767 BP
View source recordPermit 2026-112777 BP: Remove existing PVC and fanfold cover board down to original BUR mechanically attach fan fold and 50mil single-ply PVC membrane 3 Fuel · Building Permit · 2026-112777 BP
Active
Same day as the preceding date shown.
Source: Building Permit · 2026-112777 BP
View source recordTDLR Project: CapMetro Facilities Renovation Design - Vehicle Maintenance Building Phase · TDLR Project · TABS2027006448
Project Registered
77 days after the preceding date shown.
Source: TDLR Project · TABS2027006448
View source recordConstruction Start · Scheduled date
Projected start
A date supplied in the filing; this does not confirm that work started or finished.
101 days after the preceding date shown.
Source: TDLR Project · TABS2027006448
View source record
Show 1 more dates
Expected Completion · Scheduled date
Projected completion
A date supplied in the filing; this does not confirm that work started or finished.
304 days after the preceding date shown.
Source: TDLR Project · TABS2027006448
View source record
Project Metrics
TDLR #TABS2027006448Location & views
2910 E 5TH ST