๐ŸProject Closed๐Ÿ”ง Additions to Existing Building๐Ÿ’ต This project is privately funded, on private land for private use.

EAST SIDE EXPANSION EARLY RELEASE ISSUE

4TH & BOSTON AVE, Lubbock, TX 79409, Lubbock, TX, 79409
Completed100%

๐Ÿ“ŠProject Metrics

TDLR #EABPRJA9804114
$21.0M
Project Value
โ€”
Square Feet
โ€”
Cost/SqFt
8 months
Duration
Registered:Nov 13, 2008
Start:Dec 1, 2008
Target:Aug 1, 2009
๐Ÿ

Project Closed

Project has been completed and closed

๐Ÿ“‹Scope of Work

Subsurface utilities, base building foundations, elevators, and escalators, and electrical work.

Note: This project is registered under the Texas Accessibility Standards (TAS) program. TDLR registration is required for commercial and public facility construction to ensure compliance with accessibility requirements under Texas Government Code Chapter 469.

๐Ÿ“…Compliance Timeline

Project Registered
November 13, 2008
Construction Start
December 1, 2008
Expected Completion
August 1, 2009