CALDER AVE DRAINAGE IMPROVEMENTS PHASE 1

CALDER AVENUE, Beaumont, TX 77702, Beaumont, TX, 77702
Completed100%

๐Ÿ“ŠProject Metrics

TDLR #EABPRJA9804748
$23.0M
Project Value
โ€”
Square Feet
โ€”
Cost/SqFt
1y 4mo
Duration
Registered:Nov 25, 2008
Start:Jul 1, 2008
Target:Nov 1, 2009
๐Ÿ

Project Closed

Project has been completed and closed

๐Ÿ“‹Scope of Work

Reconstruct roadway, sidewalks, drainage system

Note: This project is registered under the Texas Accessibility Standards (TAS) program. TDLR registration is required for commercial and public facility construction to ensure compliance with accessibility requirements under Texas Government Code Chapter 469.

๐Ÿ“…Compliance Timeline

Project Registered
November 25, 2008
Construction Start
July 1, 2008
Expected Completion
November 1, 2009