๐ŸProject Closed๐Ÿ”ง Renovation/Alteration๐Ÿ’ต This project is privately funded, on private land for private use.

BELLMEAD UNITED PENTECOSTAL CHURCH

3109 HARRISON, Bellmead, TX 76705, Bellmead, TX, 76705
Completed100%

๐Ÿ“ŠProject Metrics

TDLR #EABPRJA9805865
$75K
Project Value
โ€”
Square Feet
โ€”
Cost/SqFt
7y 6mo
Duration
Registered:Dec 18, 2008
Start:Jan 1, 2009
Target:May 15, 2016
๐Ÿ

Project Closed

Project has been completed and closed

๐Ÿ“‹Scope of Work

REBUILD CHURCH THAT HAD BURNED DOWN

Note: This project is registered under the Texas Accessibility Standards (TAS) program. TDLR registration is required for commercial and public facility construction to ensure compliance with accessibility requirements under Texas Government Code Chapter 469.

๐Ÿ“…Compliance Timeline

Project Registered
December 18, 2008
Construction Start
January 1, 2009
Expected Completion
May 15, 2016