DUNBAR MIDDLE SCHOOL - REMOVATION

3409 STALCUP ROAD, Fort Worth, TX 76119, Fort Worth, TX, 76119
Completed100%

๐Ÿ“ŠProject Metrics

TDLR #EABPRJA9808114
$2.5M
Project Value
โ€”
Square Feet
โ€”
Cost/SqFt
1y 4mo
Duration
Registered:Feb 12, 2009
Start:May 1, 2009
Target:Aug 31, 2010
๐Ÿ

Project Closed

Project has been completed and closed

๐Ÿ“‹Scope of Work

Renovation - Includes upgrades to the school's technology including increasing the number of data drops in class

Note: This project is registered under the Texas Accessibility Standards (TAS) program. TDLR registration is required for commercial and public facility construction to ensure compliance with accessibility requirements under Texas Government Code Chapter 469.

๐Ÿ“…Compliance Timeline

Project Registered
February 12, 2009
Construction Start
May 1, 2009
Expected Completion
August 31, 2010