๐ŸProject Closed๐Ÿ—๏ธ New Construction๐Ÿ’ต This project involves public funds, public land, or is a Federally funded roadway project.

SCIENCE LAB AT NIXON HIGH SCHOOL

2000 E PLUM, Laredo, TX 78043, Laredo, TX, 78043
Completed100%

๐Ÿ“ŠProject Metrics

TDLR #EABPRJA9813810
$7.5M
Project Value
โ€”
Square Feet
โ€”
Cost/SqFt
2y 2mo
Duration
Registered:Jun 16, 2009
Start:Jul 1, 2009
Target:Aug 30, 2011
๐Ÿ

Project Closed

Project has been completed and closed

๐Ÿ“‹Scope of Work

Two story building,masonry construction,metal roof and steel roof structure w/elevator, stairs and Sci-Lab class

Note: This project is registered under the Texas Accessibility Standards (TAS) program. TDLR registration is required for commercial and public facility construction to ensure compliance with accessibility requirements under Texas Government Code Chapter 469.

๐Ÿ“…Compliance Timeline

Project Registered
June 16, 2009
Construction Start
July 1, 2009
Expected Completion
August 30, 2011