RECONSTRUCTION OF PIPELINE RD.

WEST PIPELINE RD FROM PRECINCT to Billie Ruth, Hurst, TX, 76054

Target date passed (Nov 2009)Review Complete

RECONSTRUCTION OF PIPELINE RD. is a new construction project at WEST PIPELINE RD FROM PRECINCT to Billie Ruth, Hurst, in Tarrant County, TX, tracked from its Texas Department of Licensing and Regulation (TDLR) registration. Scheduled to finish Nov 2009 per its TDLR filing; no final inspection recorded yet. The project has an estimated value of $150K.

Estimated project value
$150K
About this figure

Estimated construction cost supplied in the TDLR filing. This is not a current property appraisal or a final construction invoice.

Reported floor area
Not supplied
About this figure

Square footage reported for this scope of work. It may cover only part of a larger property.

Estimated cost / ft²
About this figure

Calculated from this filing’s estimated cost divided by its reported square footage. Available only when both figures are supplied; it is not a market benchmark.

Scheduled duration
3 months
About this figure

The interval between the filed start and completion dates. These dates describe the proposed schedule and do not measure actual construction progress.

The project record

Project timeline

Explore filed milestones and scheduled dates. Open a milestone for its source.

Jul 6, 2009118 days across supplied datesNov 1, 2009

4 timeline dates shown.

  1. Project registered · TDLR filing

    Registration of the project with the Texas Department of Licensing and Regulation.

    Source: TDLR filing

    View source record
  2. Review complete · TDLR filing

    The filing records completion of the accessibility review.

    Same day as the preceding date shown.

    Source: TDLR filing

    View source record
  3. Scheduled construction start · Scheduled date

    A date supplied in the filing; this does not confirm that work started or finished.

    26 days after the preceding date shown.

    Source: TDLR filing

    View source record
  4. Scheduled completion · Scheduled date

    A date supplied in the filing; this does not confirm that work started or finished.

    92 days after the preceding date shown.

    Source: TDLR filing

    View source record

Review Complete

Design review complete, construction may proceed

Follow this project

Get an email when the status changes — permits pulled, construction started, work finished. Free, and nothing else.

Or watch all projects in 76054 (Hurst)

One email per change. Unsubscribe in one click. Privacy.

RECONSTRUCTION OF PIPELINE RD. is a New Construction project located at WEST PIPELINE RD FROM PRECINCT to Billie Ruth, Hurst, TX 76054 in Hurst, Texas. The project has an estimated value of $150K. CITY OF HURST is the property owner and BAIRD HAMPTON & BROWN INC. is the design firm of record. The project was registered with TDLR on July 6, 2009.

Frequently Asked Questions

What is RECONSTRUCTION OF PIPELINE RD.?

RECONSTRUCTION OF PIPELINE RD. is a new construction project at WEST PIPELINE RD FROM PRECINCT to Billie Ruth in Hurst, Texas, registered with the Texas Department of Licensing and Regulation (TDLR). Scope of work: Construct new sidewalk adjacent and parallel to the newroadway

Is RECONSTRUCTION OF PIPELINE RD. open in Hurst?

RECONSTRUCTION OF PIPELINE RD. was scheduled to finish construction in Nov 2009 according to its TDLR registration, but TDLR has not recorded a final accessibility inspection, so its opening status is not confirmed in the public record.

Where is RECONSTRUCTION OF PIPELINE RD. located?

RECONSTRUCTION OF PIPELINE RD. is located at WEST PIPELINE RD FROM PRECINCT to Billie Ruth, Hurst, TX, 76054, in Tarrant County.

Who is the owner or developer of RECONSTRUCTION OF PIPELINE RD.?

CITY OF HURST is the property owner/developer of record for RECONSTRUCTION OF PIPELINE RD., per its TDLR project registration.

Who is the architect or design firm for RECONSTRUCTION OF PIPELINE RD.?

BAIRD HAMPTON & BROWN INC. is the design firm of record for RECONSTRUCTION OF PIPELINE RD., according to its TDLR filing.

How much does RECONSTRUCTION OF PIPELINE RD. cost and how big is it?

RECONSTRUCTION OF PIPELINE RD. has an estimated construction value of $150K, based on its TDLR filing.

Scope of Work

Construct new sidewalk adjacent and parallel to the newroadway

Note: This project is registered under the Texas Accessibility Standards (TAS) program. TDLR registration is required for commercial and public facility construction to ensure compliance with accessibility requirements under Texas Government Code Chapter 469.

Location & views

WEST PIPELINE RD FROM PRECINCT to Billie Ruth, Hurst, TX, 76054

Location by street address

Watch all construction in 76054 (Hurst)

A short email when anything new is filed in this ZIP. One ZIP free, weekly.

Unsubscribe in one click. Privacy.