๐ŸProject Closed๐Ÿ”ง Renovation/Alteration๐Ÿ’ต This project involves public funds, public land, or is a Federally funded roadway project.

MAJOR MAINTENANCE PROJECT

609 ARMORY ROAD, Palestine, TX 75803, Palestine, TX, 75803
Completed100%

๐Ÿ“ŠProject Metrics

TDLR #EABPRJA9816764
$644K
Project Value
โ€”
Square Feet
โ€”
Cost/SqFt
5 months
Duration
Registered:Aug 26, 2009
Start:Sep 1, 2009
Target:Feb 1, 2010
๐Ÿ

Project Closed

Project has been completed and closed

๐Ÿ“‹Scope of Work

Major maintenance including replacing interior finishes,doors & HVAC, renovating restrooms and performing minor

Note: This project is registered under the Texas Accessibility Standards (TAS) program. TDLR registration is required for commercial and public facility construction to ensure compliance with accessibility requirements under Texas Government Code Chapter 469.

๐Ÿ“…Compliance Timeline

Project Registered
August 26, 2009
Construction Start
September 1, 2009
Expected Completion
February 1, 2010