Project intelligenceTDLR EABPRJB0813443Renovation/Alteration
Funding type

This project involves public funds, public land, or is a Federally funded roadway project.

NORTHWEST RECYCLE CENTER - PHASE 2

9003 N. MAIN STREET, Houston, TX, 77022

Construction complete · Jul 2010Project Closed

NORTHWEST RECYCLE CENTER - PHASE 2 is a renovation/alteration project at 9003 N. MAIN STREET, Houston, in Harris County, TX, tracked from its Texas Department of Licensing and Regulation (TDLR) registration. Construction complete (TDLR inspection passed Jul 2010). The project has an estimated value of $685K.

Estimated project value
$685K
About this figure

Estimated construction cost supplied in the TDLR filing. This is not a current property appraisal or a final construction invoice.

Reported floor area
Not supplied
About this figure

Square footage reported for this scope of work. It may cover only part of a larger property.

Estimated cost / ft²
About this figure

Calculated from this filing’s estimated cost divided by its reported square footage. Available only when both figures are supplied; it is not a market benchmark.

Scheduled duration
1 year
About this figure

The interval between the filed start and completion dates. These dates describe the proposed schedule and do not measure actual construction progress.

The project record

Project timeline

Explore filed milestones and scheduled dates. Open a milestone for its source.

Jul 1, 2009370 days across supplied datesJul 6, 2010

4 timeline dates shown.

  1. Scheduled construction start · Scheduled date

    A date supplied in the filing; this does not confirm that work started or finished.

    Source: TDLR filing

    View source record
  2. Project closed · TDLR filing

    The project record was closed in TDLR.

    365 days after the preceding date shown.

    Source: TDLR filing

    View source record
  3. Scheduled completion · Scheduled date

    A date supplied in the filing; this does not confirm that work started or finished.

    Same day as the preceding date shown.

    Source: TDLR filing

    View source record
  4. Project registered · TDLR filing

    Registration of the project with the Texas Department of Licensing and Regulation.

    5 days after the preceding date shown.

    Source: TDLR filing

    View source record

Project Closed

Project has been completed and closed

Follow this project

Get an email when the status changes — permits pulled, construction started, work finished. Free, and nothing else.

Or watch all projects in 77022 (Houston)

One email per change. Unsubscribe in one click. Privacy.

NORTHWEST RECYCLE CENTER - PHASE 2 is a Renovation/Alteration project located at 9003 N. MAIN STREET, Houston, TX 77022 in Houston, Texas. The project has an estimated value of $685K. CITY OF HOUSTON is the property owner and JACOBS is the design firm of record. The project was registered with TDLR on July 6, 2010.

Frequently Asked Questions

What is NORTHWEST RECYCLE CENTER - PHASE 2?

NORTHWEST RECYCLE CENTER - PHASE 2 is a renovation/alteration project at 9003 N. MAIN STREET in Houston, Texas, registered with the Texas Department of Licensing and Regulation (TDLR). Scope of work: Demolish portion of existing recycle center and replacewith new elevated vehicle dump area and new stand alone

Is NORTHWEST RECYCLE CENTER - PHASE 2 open in Houston?

Construction on NORTHWEST RECYCLE CENTER - PHASE 2 is complete — TDLR records show the project passed its required accessibility inspection in Jul 2010. The building is finished and very likely open.

Where is NORTHWEST RECYCLE CENTER - PHASE 2 located?

NORTHWEST RECYCLE CENTER - PHASE 2 is located at 9003 N. MAIN STREET, Houston, TX, 77022, in Harris County.

Who is the owner or developer of NORTHWEST RECYCLE CENTER - PHASE 2?

CITY OF HOUSTON is the property owner/developer of record for NORTHWEST RECYCLE CENTER - PHASE 2, per its TDLR project registration.

Who is the architect or design firm for NORTHWEST RECYCLE CENTER - PHASE 2?

JACOBS is the design firm of record for NORTHWEST RECYCLE CENTER - PHASE 2, according to its TDLR filing.

How much does NORTHWEST RECYCLE CENTER - PHASE 2 cost and how big is it?

NORTHWEST RECYCLE CENTER - PHASE 2 has an estimated construction value of $685K, based on its TDLR filing.

Scope of Work

Demolish portion of existing recycle center and replacewith new elevated vehicle dump area and new stand alone

Note: This project is registered under the Texas Accessibility Standards (TAS) program. TDLR registration is required for commercial and public facility construction to ensure compliance with accessibility requirements under Texas Government Code Chapter 469.

Location & views

9003 N. MAIN STREET, Houston, TX, 77022

29.82968, -95.39839

Watch all construction in 77022 (Houston)

A short email when anything new is filed in this ZIP. One ZIP free, weekly.

Unsubscribe in one click. Privacy.