๐ŸProject Closed๐Ÿ”ง Renovation/Alteration๐Ÿ’ต This project is privately funded, on private land for private use.

GE TRANSPORTATION-PROJECT FORWARD

12850 THREE WIDE DR, Fort Worth, TX 76177, Fort Worth, TX, 76177
Completed100%

๐Ÿ“ŠProject Metrics

TDLR #EABPRJB1815556
$50.0M
Project Value
โ€”
Square Feet
โ€”
Cost/SqFt
1y 2mo
Duration
Registered:Jul 21, 2011
Start:Aug 1, 2011
Target:Sep 30, 2012
๐Ÿ

Project Closed

Project has been completed and closed

๐Ÿ“‹Scope of Work

Deisel Locomotive production facility consisting of: 1)Site / shell modifications and interior improvements to

Note: This project is registered under the Texas Accessibility Standards (TAS) program. TDLR registration is required for commercial and public facility construction to ensure compliance with accessibility requirements under Texas Government Code Chapter 469.

๐Ÿ“…Compliance Timeline

Project Registered
July 21, 2011
Project Closed
September 30, 2012
Construction Start
August 1, 2011
Expected Completion
September 30, 2012