SMU PLANO RECOVERY DATA CENTER
SMU PLANO RECOVERY DATA CENTER is a renovation/alteration project at 5236 TENNYSON PARKWAY, Plano, in Collin County, TX, tracked from its Texas Department of Licensing and Regulation (TDLR) registration. Construction complete (TDLR inspection passed Dec 2011). The project has an estimated value of $1.5M.
๐Project Metrics
TDLR #EABPRJB2800842Project Closed
Project has been completed and closed
SMU PLANO RECOVERY DATA CENTER is a Renovation/Alteration project located at 5236 TENNYSON PARKWAY, Plano, TX 75024 in Plano, Texas. The project has an estimated value of $1.5M. SMU is the property owner and PGAL is the design firm of record. The project was registered with TDLR on September 20, 2011.
โFrequently Asked Questions
What is SMU PLANO RECOVERY DATA CENTER?
SMU PLANO RECOVERY DATA CENTER is a renovation/alteration project at 5236 TENNYSON PARKWAY in Plano, Texas, registered with the Texas Department of Licensing and Regulation (TDLR). Scope of work: Renovation of an existing building lease space and turning into a data center for the university.
Is SMU PLANO RECOVERY DATA CENTER open in Plano?
Construction on SMU PLANO RECOVERY DATA CENTER is complete โ TDLR records show the project passed its required accessibility inspection in Dec 2011. The building is finished and very likely open.
Where is SMU PLANO RECOVERY DATA CENTER located?
SMU PLANO RECOVERY DATA CENTER is located at 5236 TENNYSON PARKWAY, Plano, TX, 75024, in Collin County.
Who is the owner or developer of SMU PLANO RECOVERY DATA CENTER?
SMU is the property owner/developer of record for SMU PLANO RECOVERY DATA CENTER, per its TDLR project registration.
Who is the architect or design firm for SMU PLANO RECOVERY DATA CENTER?
PGAL is the design firm of record for SMU PLANO RECOVERY DATA CENTER, according to its TDLR filing.
How much does SMU PLANO RECOVERY DATA CENTER cost and how big is it?
SMU PLANO RECOVERY DATA CENTER has an estimated construction value of $1.5M, based on its TDLR filing.
๐Scope of Work
Renovation of an existing building lease space and turning into a data center for the university.
Note: This project is registered under the Texas Accessibility Standards (TAS) program. TDLR registration is required for commercial and public facility construction to ensure compliance with accessibility requirements under Texas Government Code Chapter 469.
๐ Compliance Timeline
๐ Project Timeline
Filed
Sep 20, 2011
Review Complete
Inspection Complete
Closed
Dec 1, 2011