๐Project Closed๐ง Renovation/Alteration๐ต This project involves public funds, public land, or is a Federally funded roadway project.
BEECHNUT STREET - KIRKWOOD TO WILCREST
10900 TO 11800 BEECHNUT STREET 8000 to 8600 Kirkwood Road, Houston, TX 77472, Houston, TX, 77472
Completed100%
๐Project Metrics
TDLR #EABPRJB2809989$250K
Project Value
โ
Square Feet
โ
Cost/SqFt
2y 2mo
Duration
Registered:Mar 23, 2012
Start:Sep 1, 2012
Target:Nov 1, 2014
๐
Project Closed
Project has been completed and closed
๐Scope of Work
Replacement of existing concrete street and concrete sidewalks, and the upgrade of the storm sewer systemm snait
Note: This project is registered under the Texas Accessibility Standards (TAS) program. TDLR registration is required for commercial and public facility construction to ensure compliance with accessibility requirements under Texas Government Code Chapter 469.
๐ Compliance Timeline
Project Registered
March 23, 2012
Construction Start
September 1, 2012
Expected Completion
November 1, 2014
๐Related Projects
๐คSame Owner
$4.8M totalProperty Owner
๐ค
CITY OF HOUSTON- PUBLIC WORKS DEPARTMENT
2 projects ยท $4.8M
View all projects
MIKE CORDOVA, SR. PROJECT MANA P.O. BOX 1562, HOUSTON, TX 77251
Design Firm
๐๏ธ
JONES & CARTER INC.
4 projects ยท $1.2M
View all projects
DONALD M. DURGIN, P.E. 6335 GULFTON SUITE 100, HOUSTON, T 77081