Project intelligenceTDLR EABPRJB2814629Renovation/Alteration
Funding type

This project is privately funded, on private land for private use.

2ND FLOOR FINISH-OUT ACTIVITY CENTER in Mcallen, TX

300 WEST PECAN BLVD., Mcallen, TX, 78501

Construction complete · Nov 2012Project Closed

2ND FLOOR FINISH-OUT ACTIVITY CENTER is a renovation/alteration project at 300 WEST PECAN BLVD., Mcallen, in Hidalgo County, TX, tracked from its Texas Department of Licensing and Regulation (TDLR) registration. Construction complete (TDLR inspection passed Nov 2012). The project has an estimated value of $700K.

Estimated project value
$700K
About this figure

Estimated construction cost supplied in the TDLR filing. This is not a current property appraisal or a final construction invoice.

Reported floor area
Not supplied
About this figure

Square footage reported for this scope of work. It may cover only part of a larger property.

Estimated cost / ft²
—
About this figure

Calculated from this filing’s estimated cost divided by its reported square footage. Available only when both figures are supplied; it is not a market benchmark.

Scheduled duration
4 months
About this figure

The interval between the filed start and completion dates. These dates describe the proposed schedule and do not measure actual construction progress.

The project record

Project timeline

Explore filed milestones and scheduled dates. Open a milestone for its source.

Jun 13, 2012141 days across supplied datesNov 1, 2012

4 timeline dates shown.

  1. Project registered · TDLR filing

    Registration of the project with the Texas Department of Licensing and Regulation.

    Source: TDLR filing

    View source record
  2. Scheduled construction start · Scheduled date

    A date supplied in the filing; this does not confirm that work started or finished.

    18 days after the preceding date shown.

    Source: TDLR filing

    View source record
  3. Project closed · TDLR filing

    The project record was closed in TDLR.

    123 days after the preceding date shown.

    Source: TDLR filing

    View source record
  4. Scheduled completion · Scheduled date

    A date supplied in the filing; this does not confirm that work started or finished.

    Same day as the preceding date shown.

    Source: TDLR filing

    View source record

Project Closed

Project has been completed and closed

Follow this project

Get an email when the status changes — permits pulled, construction started, work finished. Free, and nothing else.

Or watch all projects in 78501 (Mcallen)

One email per change. Unsubscribe in one click. Privacy.

2ND FLOOR FINISH-OUT ACTIVITY CENTER is a Renovation/Alteration project located at 300 WEST PECAN BLVD., Mcallen, TX 78501 in Mcallen, Texas. The project has an estimated value of $700K. ST. PAUL LUTHERAN CHURCH is the property owner and BOULTINGHOUSE SIMPSON & ASSOC. INC. is the design firm of record. The project was registered with TDLR on June 13, 2012.

Frequently Asked Questions

What is 2ND FLOOR FINISH-OUT ACTIVITY CENTER?

2ND FLOOR FINISH-OUT ACTIVITY CENTER is a renovation/alteration project at 300 WEST PECAN BLVD. in Mcallen, Texas, registered with the Texas Department of Licensing and Regulation (TDLR). Scope of work: interior finish-out of existing unfinished 2nd floor forclassrooms

Is 2ND FLOOR FINISH-OUT ACTIVITY CENTER open in Mcallen?

Construction on 2ND FLOOR FINISH-OUT ACTIVITY CENTER is complete — TDLR records show the project passed its required accessibility inspection in Nov 2012. The building is finished and very likely open.

Where is 2ND FLOOR FINISH-OUT ACTIVITY CENTER located?

2ND FLOOR FINISH-OUT ACTIVITY CENTER is located at 300 WEST PECAN BLVD., Mcallen, TX, 78501, in Hidalgo County.

Who is the owner or developer of 2ND FLOOR FINISH-OUT ACTIVITY CENTER?

ST. PAUL LUTHERAN CHURCH is the property owner/developer of record for 2ND FLOOR FINISH-OUT ACTIVITY CENTER, per its TDLR project registration.

Who is the architect or design firm for 2ND FLOOR FINISH-OUT ACTIVITY CENTER?

BOULTINGHOUSE SIMPSON & ASSOC. INC. is the design firm of record for 2ND FLOOR FINISH-OUT ACTIVITY CENTER, according to its TDLR filing.

How much does 2ND FLOOR FINISH-OUT ACTIVITY CENTER cost and how big is it?

2ND FLOOR FINISH-OUT ACTIVITY CENTER has an estimated construction value of $700K, based on its TDLR filing.

Scope of Work

interior finish-out of existing unfinished 2nd floor forclassrooms

Note: This project is registered under the Texas Accessibility Standards (TAS) program. TDLR registration is required for commercial and public facility construction to ensure compliance with accessibility requirements under Texas Government Code Chapter 469.

Location & views

300 WEST PECAN BLVD., Mcallen, TX, 78501

Location by street address

Watch all construction in 78501 (Mcallen)

A short email when anything new is filed in this ZIP. One ZIP free, weekly.

Unsubscribe in one click. Privacy.